Hoover, Inc. v. Ashby Communities, LLC
M2016-01877-COA-R3-CV
| Tenn. Ct. App. | Nov 28, 2017Background
- Hoover, an asphalt/paving contractor, submitted proposals in Oct–Nov 2009 and began work at King’s Chapel subdivision on Nov 12, 2009; Ashby accepted Hoover’s proposals and Powell guaranteed credit.
- Hoover billed $92,588.22 for November 2009 work; Ashby did not pay and Hoover stopped work Dec 14, 2009, later recording a mechanic’s lien and suing for the unpaid invoice, interest, and attorney’s fees.
- Ashby asserted multiple defenses and counterclaimed (breach, TCPA, misrepresentation); Land Investment Group (LIG) was subsequently joined and raised related claims about the lien and title.
- At trial the court found Ashby breached the contract first by refusing to pay the November invoice, awarded Hoover principal ($89,739.52), contractual interest (1.5%/mo to June 30, 2016), and attorney’s fees ($59,559.42).
- The court rejected Ashby’s claims that Hoover materially underperformed or that road failures proved Hoover’s breach, finding evidence did not show Hoover caused the later deficiencies.
- On appeal the Court of Appeals affirmed: contract interpreted to require payment for “all work performed” each month; any overbilling was negligible; fee and interest awards were supported and within discretion.
Issues
| Issue | Plaintiff's Argument (Hoover) | Defendant's Argument (Ashby) | Held |
|---|---|---|---|
| Whether court improperly reformed the contract to reduce roads from five to three | Contract was valid as written; payment based on work performed per month | Court sua sponte reformed contract (Ashby) and that was error | Court did not reform contract; held payment is for “all work performed” monthly and road-count issue was not determinative; no reformation error |
| Which party committed the first material breach (nonpayment vs. overbilling/underperformance) | Hoover billed for work performed in Nov. 2009 and was entitled to payment; overbilling negligible | Ashby: Hoover overbilled (claimed ~70% billed though <50% complete); Hoover first breached by inaccurate billing | Trial court’s factual finding that Ashby refused to pay the Nov. invoice stands; evidence does not preponderate against that finding — Ashby first breached by nonpayment |
| Validity of Ashby’s counterclaims that Hoover’s work was deficient (breach/TCPA/misrepresentation) | Hoover: later road failures attributable to other contractors/flooding; Hoover only laid what it did before leaving | Ashby: road failures and GEOServices’ testing show Hoover failed to place required base stone and therefore breached | Court found Ashby failed to prove deficiencies were Hoover’s fault; expert testimony was speculative and other contractors/flooding likely explanations; counterclaims rejected |
| Award of attorney’s fees and interest (reasonableness and accrual date) | Fees and contractual interest proper; litigation length partly due to defendants’ tactics; counsel’s affidavit and cross-examination sufficient | Ashby: trial court improperly relied on case duration; lacked billing records and meaningful cross-examination; interest award inequitable/should start later | Court applied proper standard (Tenn. Sup. Ct. R. 8 factors); fee award not an abuse of discretion; interest was contractual (1.5%/mo) and properly applied from due date |
Key Cases Cited
- Watson v. Watson, 196 S.W.3d 695 (Tenn. Ct. App. 2005) (standard for appellate review of bench trial findings)
- Campbell v. Florida Steel Corp., 919 S.W.2d 26 (Tenn. 1996) (deference and standard for appellate review of trial court findings)
- Morrison v. Allen, 338 S.W.3d 417 (Tenn. 2011) (trial court’s advantage in witness credibility determinations)
- Wright ex rel. Wright v. Wright, 337 S.W.3d 166 (Tenn. 2011) (standard of review and guidance on attorney’s fee awards)
- Konvalinka v. Chattanooga–Hamilton Cnty. Hosp. Auth., 249 S.W.3d 346 (Tenn. 2008) (abuse of discretion framework for reviewing discretionary trial-court rulings)
- White v. McBride, 937 S.W.2d 796 (Tenn. 1996) (reasonableness of fees depends on case circumstances)
