History
  • No items yet
midpage
Hoosier Environmental Council v. United States Army Corps of Engineers
722 F.3d 1053
7th Cir.
2013
Read the full case

Background

  • Federal, state, and local agencies proposed completing I-69 by building a new direct interstate segment between Indianapolis and Evansville; section 3 (26 miles) was constructed and is at issue.
  • The Army Corps of Engineers issued a Clean Water Act §404 permit allowing wetland fills and six stream crossings in section 3; plaintiffs challenged only the wetlands/stream-fill aspects under §404.
  • Plaintiffs argued the Corps should have treated the entire direct-route project (all six sections) as the unit of analysis and rejected it in favor of upgrading the existing indirect route (Route 41) as a practicable, less-damaging alternative.
  • Agencies conducted a two-tier NEPA/Tiered EIS process: Tier I selected a 2,000-foot corridor (direct route preferred); Tier II addressed alignments and wetland impacts section-by-section; Corps relied on Tier I/Tier II analyses in permitting section 3.
  • The district court granted summary judgment to the defendants; plaintiffs appealed. The Corps analyzed alternatives and public-interest factors for section 3 and required wetland mitigation/recreation.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Scope of Corps' duty to consider practicable alternatives under §404 Corps had to compare the entire direct route to the indirect route and could not limit analysis to one section; indirect route was practicable Corps may rely on Tier I corridor decision and need only evaluate practicable alternatives relevant to the specific permit (section-level alignments or no-build) Corps properly relied on Tier I/Tier II analyses; need not re-evaluate whole-route practicability when another agency already performed responsible analysis
Whether the indirect route was a "practicable alternative" Indirect (upgrade Route 41) was cheaper and environmentally superior and met overall project purposes Indirect route failed to meet overall project purposes (shorter route, access, accident reduction); Corps could accept FHWA/INDOT determinations Tier I analysis reasonably found indirect route impracticable; Corps permissibly relied on that finding
Improper segmentation / piecemeal analysis of environmental impacts Section-by-section permitting improperly segmented cumulative impacts of whole project Tiering/sectioning was reasonable and necessary; Tier I assessed corridor-level wetlands and Tier II analyzed site-specific impacts Segmenting into Tier I/Tier II and section-by-section permits was permissible; not improper segmentation here
Adequacy of Corps' public-interest review under 33 C.F.R. §320.4 Corps failed to perform a public-interest analysis of the entire project and thus could not conclude section 3 was in the public interest Corps weighed numerous public-interest factors for section 3 and reasonably relied on the highway agencies' broader NEPA analyses Corps conducted a sufficiently detailed public-interest analysis for section 3 and its reliance on other agencies' studies was reasonable

Key Cases Cited

  • Decker v. Northwest Environmental Defense Center, 133 S. Ct. 1326 (2013) (mootness requires impossibility of effective relief)
  • Klemme v. Sierra Club, 427 U.S. 390 (1976) (permissible administrative tiering on complex projects)
  • United States v. Alaska, 503 U.S. 569 (1992) (regulatory public-interest requirements interpreted literally)
  • Van Abbema v. Fornell, 807 F.2d 633 (7th Cir. 1986) (Corps may rely on applicants’/consultants’ submissions and need not perform independent investigations)
  • Hillsdale Environmental Loss Prevention, Inc. v. U.S. Army Corps of Engineers, 702 F.3d 1156 (10th Cir. 2012) (remedies related to unlawful wetlands fills can include restoration injunctions)
Read the full case

Case Details

Case Name: Hoosier Environmental Council v. United States Army Corps of Engineers
Court Name: Court of Appeals for the Seventh Circuit
Date Published: Jul 16, 2013
Citation: 722 F.3d 1053
Docket Number: 12-3187
Court Abbreviation: 7th Cir.