History
  • No items yet
midpage
Honeywell International, Inc.
ASBCA No. 57779
| A.S.B.C.A. | Aug 1, 2017
Read the full case

Background

  • The Army issued an ESPC delivery order to Honeywell (2008) covering energy conservation measures at Fort Dix, including two 700 kW solar arrays (Phase I roof-mounted; Phase II ground-mounted). Payments were scheduled over 21 years.
  • The DO computed government savings by combining electricity value and Solar Renewable Energy Certificate (SREC) sale value; Honeywell could sell SRECs for the government and guaranteed annual savings.
  • The Board previously held (2013) that SREC revenues could not be included as cognizable ESPC savings and invalidated the DO provisions permitting SREC sales; later (2015) the Board recognized Honeywell could seek quantum valebant/quantum meruit for benefits delivered.
  • Honeywell completed Phase I (accepted 2009) and delivered Phase II (installed 2010) though the government did not connect or accept Phase II; the government later issued a final decision cancelling the solar portions of the DO (2011).
  • The DO schedules listed implementation prices ($6,485,901 Phase I; $5,304,278 Phase II), financing rates (6.19% Phase I; 8.95% Phase II), and contained a cancellation ceiling/financing termination schedule (106.5% financing termination fee). Phase II SRECs were shown to have market value of $2,553,728 (unrefuted).

Issues

Issue Honeywell's Argument Government's Argument Held
1) Whether SREC revenues could be counted as government "savings" under the DO DO included SREC value; Honeywell relied on DO calculations SREC sales not cognizable ESPC savings; contracting officers lacked authority Board previously invalidated inclusion of SREC revenues in ESPC savings (SRECs excluded)
2) Proper measure of quantum valebant/meruit for delivered arrays The DO schedules fix the arrays' values (implementation prices), plus financing and termination fee — total recovery per schedules Government expert valued Phase II far lower using different degradation, wholesale rate, and escalation assumptions Board used DO implementation prices but subtracted SREC value and profit (7%) to arrive at baseline values for each phase ($3,656,921 Phase I; $2,558,011 Phase II)
3) Whether Honeywell may recover financing interest and from which dates Interest should accrue per DO financing rates from award/dates asserted by Honeywell Government limits or disputes pre-delivery/early accrual and scope of financing benefit Interest awarded at agreed DO rates: Phase I at 6.19% from 31 Jul 2009 to 21 Jun 2011; Phase II at 8.95% from 15 Apr 2010 to 21 Jun 2011; CDA interest thereafter until payment
4) Recovery of contractual termination premium, monitoring panel, and prorated design costs Recovery should include 6.5% financing termination fee, monitoring panel, prorated feasibility/design amounts Termination schedule set maxima; actual termination/convenience costs must be negotiated; monitoring panel not in CO claim; insufficient proof on prorated design costs Board denied entitlement to termination premium and monitoring panel; rejected prorated feasibility/design recovery for lack of proof and jurisdictional/claim limitations

Key Cases Cited

  • United States v. Amdahl Corp., 786 F.2d 387 (Fed. Cir. 1986) (quantum valebant/meruit limited to value of benefits conferred prior to rescission)
  • Pacific Maritime Ass'n v. United States, 108 F. Supp. 603 (Ct. Cl. 1952) (contract price can guide measure of value conferred where government received benefit)
  • Urban Data Sys., Inc. v. United States, 699 F.2d 1147 (Fed. Cir. 1983) (addresses reliance on agreed prices when no valid contract existed)
Read the full case

Case Details

Case Name: Honeywell International, Inc.
Court Name: Armed Services Board of Contract Appeals
Date Published: Aug 1, 2017
Docket Number: ASBCA No. 57779
Court Abbreviation: A.S.B.C.A.