History
  • No items yet
midpage
119 F.4th 920
11th Cir.
2024
Read the full case

Background

  • Corporación AIC, S.A. (AICSA) and Hidroeléctrica Santa Rita S.A. (HSR), both Guatemalan companies, entered into an EPC Contract for AICSA to build a hydroelectric plant in Guatemala.
  • Construction was halted due to local community opposition and threats, leading HSR to suspend and later terminate the contract, citing force majeure.
  • Arbitration was initiated by HSR seeking return of advance payments and other damages; AICSA counterclaimed and sought to join its subcontractor, Novacom, to the proceedings.
  • The arbitral tribunal ruled partially for both parties, dismissed AICSA’s bribery-based claims, refused to join Novacom, and clarified AICSA must replace expired payment bonds.
  • AICSA sought to vacate the arbitral award in U.S. court, arguing the tribunal exceeded its authority; the district court confirmed the award, leading to this appeal.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Tribunal's authority to require new Advance Payment Bonds AICSA: Tribunal exceeded authority by mandating new bonds if originals lapsed HSR: Tribunal interpreted the contract, as it allowed bonds to be maintained Tribunal acted within its authority; decision upheld
Tribunal's denial of AICSA's anti-corruption/breach claim AICSA: Tribunal exceeded authority in denying FCPA-based breach claim HSR: Tribunal lacked jurisdiction and evidence for a FCPA private action Tribunal interpreted the contract/FCPA; no excess of authority
Refusal to join Novacom to arbitration AICSA: Tribunal misinterpreted contract by denying Novacom's joinder HSR: EPC Contract did not permit third-party asserted claims in arbitration Tribunal's contract-based interpretation was within authority

Key Cases Cited

  • Oxford Health Plans LLC v. Sutter, 569 U.S. 564 (arbitrator’s contract interpretation must stand if even arguably based on the contract)
  • United Paperworkers Int’l Union, AFL-CIO v. Misco, Inc., 484 U.S. 29 (courts cannot vacate arbitration awards for mere legal error; arbitrator must act beyond authority)
  • Stolt-Nielsen S.A. v. AnimalFeeds Int’l Corp., 559 U.S. 662 (arbitrator exceeds authority only when acting outside the bounds of the contract)
  • E. Associated Coal Corp. v. United Mine Workers of Am., Dist. 17, 531 U.S. 57 (arbitration awards grounded in contract interpretation are deferred to by courts)
  • Enter. Wheel & Car Corp., 363 U.S. 593 (finality of arbitral interpretation must be honored by courts)
Read the full case

Case Details

Case Name: Hidroelectrica Santa Rita S.A. v. Corporacion AIC, SA
Court Name: Court of Appeals for the Eleventh Circuit
Date Published: Oct 16, 2024
Citations: 119 F.4th 920; 23-12519
Docket Number: 23-12519
Court Abbreviation: 11th Cir.
Log In