History
  • No items yet
midpage
Hess v. Pennsylvania Public Utility Commission
107 A.3d 246
| Pa. Commw. Ct. | 2014
Read the full case

Background

  • PPL Electric sought Commission approval under 15 Pa.C.S. § 1511(c) to condemn easements across protestants’ land to build an 11.54‑mile, 69 kV transmission tie line and a new 69/12 kV substation to improve local transmission and distribution reliability.
  • PPL relied on its internal Reliability Principles & Practices (RP & P) Guidelines and PJM review to show current reliability violations and that smaller fixes had not resolved the problems; estimated project cost ~$12 million.
  • Protestants and intervenors contested necessity and alternatives, offering expert testimony that reconductoring or using existing rights‑of‑way would be less intrusive and sufficient.
  • Two ALJs recommended denying PPL’s applications, finding PPL had not shown the type of ‘‘need’’ recognized in prior cases involving NERC/PJM mandates.
  • The Pennsylvania PUC reversed in part: it struck protestants’ late extra‑record evidence, approved the route, and found PPL’s combined transmission and substation proposal was necessary or proper based on RP & P violations, exhaustion of lesser measures, consideration of alternatives, and PJM review.
  • Commonwealth Court affirmed the PUC (majority), holding (1) NERC/PJM mandatory standards do not apply to sub‑100 kV non‑BES facilities and therefore PPL’s RP & P evidence was a permissible basis for necessity; (2) the PUC reasonably found PPL considered alternatives; and (3) striking late evidence was proper. A dissent argued environmental impact and Payne v. Kassab analysis should have barred approval.

Issues

Issue Plaintiff's Argument (Protestants) Defendant's Argument (PPL/PUC) Held
Whether PPL’s RP & P violations can establish "necessity" under §1511(c) Necessity requires mandatory external standards or directives (e.g., NERC/PJM); self‑imposed guidelines alone are insufficient RP & P Guidelines are required planning criteria, consistent with PJM/NERC practice for non‑BES planning and can show current, substantial reliability issues Held: RP & P evidence may establish necessity for sub‑100 kV projects; TrAILCo/Susquehanna‑Roseland (PJM/NERC) are inapplicable to non‑BES lines; PUC’s broader standard affirmed
Standard of "necessity" — must it be "absolute" (imminent overload) Need must be ‘‘absolute’’ (imminent overload or mandatory directive) before condemnation Statutory and precedent law permit finding necessity where a project improves reliability, reduces outage duration/impact, and smaller measures fail Held: Rejected the "absolute necessity" test; proactive reliability improvements are proper bases for condemnation
Whether PPL adequately considered and rejected reasonable alternatives Protestants’ alternatives (reconductoring, double‑circuit on existing ROW, third feeder) were superior, less costly, less intrusive PPL evaluated alternatives, found them infeasible, costlier, or unable to meet load‑transfer/reliability objectives; PUC credited PPL witnesses Held: Substantial evidence supports PUC’s finding that PPL considered alternatives and its plan was the best available
Whether Commission properly struck protestants’ extra‑record quarterly reports in Reply to Exceptions The quarterly reliability reports were public filings and would show PPL’s worst‑circuit claim was misleading; allowing them corrects the record Introducing new facts after the record closed deprived PPL of opportunity to respond; procedural fairness/due process required striking them Held: Commission did not abuse discretion in striking late evidence; protestants should have introduced or challenged that evidence during hearings

Key Cases Cited

  • Energy Conservation Council of Pennsylvania v. Pa. Pub. Utility Comm'n, 995 A.2d 465 (Pa. Cmwlth. 2010) (utility must show need to remedy reliability/NERC‑PJM violations in certain high‑voltage contexts)
  • Energy Conservation Council of Pennsylvania v. Pa. Pub. Utility Comm'n, 25 A.3d 440 (Pa. Cmwlth. 2011) (Susquehanna‑Roseland) (PJM directive justified need for high‑voltage project)
  • Riverwalk Casino, L.P. v. Pa. Gaming Control Board, 926 A.2d 926 (Pa. 2007) (agency technical determinations entitled to strong deference)
  • Popowsky v. Pa. Public Utility Comm'n, 706 A.2d 1197 (Pa. 1998) (Commission is ultimate factfinder; credibility determinations are for the agency)
  • Pa. Power & Light Co. v. Pa. Pub. Utility Comm'n, 696 A.2d 248 (Pa. Cmwlth. 1997) (necessity test should consider public power needs, technology, and alternatives rather than only engineering perspective)
  • Payne v. Kassab, 312 A.2d 86 (Pa. Cmwlth. 1973) (environmental impact balancing test for public‑utility projects)
  • Robinson Township v. Pa. Pub. Utility Comm'n, 83 A.3d 901 (Pa. 2013) (Environmental Rights Amendment requires advance consideration of environmental effects)
Read the full case

Case Details

Case Name: Hess v. Pennsylvania Public Utility Commission
Court Name: Commonwealth Court of Pennsylvania
Date Published: Dec 22, 2014
Citation: 107 A.3d 246
Court Abbreviation: Pa. Commw. Ct.