History
  • No items yet
midpage
Heskett Ins. Agency, Inc. v. Braunlin
2011 Ohio 6100
Ohio Ct. App.
2011
Read the full case

Background

  • Heskett and Braunlin entered a settlement reducing to writing, with Braunlin to pay $25,000 in eight installments and to pay liquidated damages on late payments.
  • Settlement provided a specific schedule from 2006 to 2007 and required delivery to Heskett at designated addresses; payments must be timely.
  • Heskett claimed Braunlin made four late payments (three before dates but allegedly delivered early by mail) and sought liquidated damages totaling $11,000 plus $5,000 already paid.
  • Trial court found the mailbox rule did not apply and that payments were late because they were received after due dates.
  • Court also held the liquidated damages clause not an unenforceable penalty and awarded $11,000; later proceedings led to discovery of bankruptcy-discharge implications.
  • On appeal, the court reversed the liquidated-damages award, remanding for actual damages, and affirmed the breach findings tied to late payments.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Does 'delivered' mean delivery is complete only when received by Heskett? Braunlin: mailing before due dates constitutes timely delivery. Heskett: payment must be received by due date to be timely. Timely payment requires receipt on or before due date.
Should unclean hands bar liquidated damages? Braunlin: Heskett acted in bad faith penalizing mail delivery. Heskett: clean hands doctrine not invoked; damages are contractual. Unclean hands doctrine does not apply; damages recovery remains legal remedy.
Are the liquidated damages provisions enforceable or penalties? Braunlin: clause is unenforceable as a penalty because damages are certain. Heskett: clause legitimately doubles late payments as liquidated damages. Liquidated damages clause is an unenforceable penalty; remand for actual damages.

Key Cases Cited

  • Continental West Condominium Unit Owners Assn. v. Howard E. Ferguson, Inc., 74 Ohio St.3d 501 (1996) (interpretation of settlement agreements and contract principles)
  • Jones v. Stevens, 112 Ohio St.43 (1925) (test for whether liquidated damages are penalties)
  • Lake Ridge Academy v. Carney, 66 Ohio St.3d 376 (1993) (criteria for distinguishing liquidated damages from penalties)
  • Latina v. Woodpath Development Co., 57 Ohio St.3d 212 (1991) (statutory interpretation and contract meaning guidance)
Read the full case

Case Details

Case Name: Heskett Ins. Agency, Inc. v. Braunlin
Court Name: Ohio Court of Appeals
Date Published: Nov 16, 2011
Citation: 2011 Ohio 6100
Docket Number: 11CA3234
Court Abbreviation: Ohio Ct. App.