HECO Pacific Manufacturing, Inc.
63217
A.S.B.C.A.Sep 4, 2025Background
- HECO Pacific had a fixed‑price delivery order to supply three cranes at Naval Base Kitsap; work was suspended in March 2019 over paint issues.
- HECO submitted REAs in Nov. 2019 and a revised Dec. 2019 REA for delay impacts; both predated or expressly excluded COVID costs.
- On Sept. 3, 2020 HECO submitted a new REA (explicitly excluding COVID costs); on Sept. 17, 2020 the government executed Modification No. 07 increasing price and extending performance to April 30, 2021 and containing broad release/accord language settling the identified REAs.
- In Dec. 2020 the government issued COVID access/restriction requirements for the project.
- HECO submitted a COVID‑related REA/claim in Sept.–Nov. 2021 for additional costs from complying with base COVID rules; the government denied the claim and HECO appealed to the ASBCA.
- The government moved for summary judgment arguing (1) release/accord & satisfaction bars the claim, (2) COVID impacts were unforeseeable, and (3) the COVID requirements are sovereign acts; the Board denied the motion.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether Modification No. 07 (and its release language) bars HECO’s COVID‑related claim | Mod settled only the REAs identified (which excluded COVID costs) and did not release costs arising from COVID requirements imposed after the modification | Mod’s accord and satisfaction/release language settled all costs, impacts and delays arising out of the revised work | Denied: modification’s plain language and incorporated REAs do not show meeting of the minds to surrender post‑modification COVID costs |
| Whether government is relieved because COVID impacts were unforeseeable when initial delays began | HECO frames claim as recovery for government delays that pushed performance into the COVID period (analogous to weather delay cases) rather than direct liability for sovereign COVID rules | Government says delay liability cannot extend to unforeseeable COVID impacts that occurred after initial delay began | Denied (fact question): the Board rejects a categorical rule that foreseeability must be judged only as of the initial delay date and declines summary judgment on foreseeability grounds |
| Whether the government’s COVID access requirements are sovereign acts that bar recovery | HECO asserts its claim is for government delay forcing performance into the pandemic period; even if COVID rules are sovereign, delay consequences may be compensable | Government contends the COVID requirements were public, general sovereign acts insulating it from contract liability | Denied: government failed to prove requirements were public/general sovereign acts or that the issuing official had authority to impose sovereign acts; record insufficient for summary judgment |
| Whether summary judgment is appropriate overall | HECO maintains genuine disputes of material fact remain (scope of release, foreseeability, sovereign character) | Government seeks judgment as a matter of law based on release, foreseeability precedent, and sovereign acts doctrine | Denied: factual disputes and insufficient evidentiary showing by government preclude summary judgment |
Key Cases Cited
- Bell BCI Co. v. United States, 570 F.3d 1337 (Fed. Cir.) (accord and satisfaction/release principles)
- Meridian Eng’g Co. v. United States, 885 F.3d 1351 (Fed. Cir.) (fact‑specific inquiry into meeting of the minds for accord and satisfaction)
- Stockton E. Water Dist. v. United States, 583 F.3d 1344 (Fed. Cir.) (sovereign acts doctrine and limits on holding government liable for public acts)
- Casitas Mun. Water Dist. v. United States, 543 F.3d 1276 (Fed. Cir.) (sovereign acts may bar liability when acts are public/general and render performance impossible)
- Connor Bros. Constr. Co. v. Geren, 550 F.3d 1368 (Fed. Cir.) (sovereign acts as an affirmative defense; scope of acts relevant)
- Horowitz v. United States, 267 U.S. 458 (U.S.) (government’s immunity for sovereign acts)
- Dairyland Power Coop. v. United States, 16 F.3d 1197 (Fed. Cir.) (summary judgment movant is not entitled to favorable inferences)
