History
  • No items yet
midpage
HCS, Inc.
ASBCA No. 60533
| A.S.B.C.A. | Sep 20, 2016
Read the full case

Background

  • Navy issued a firm-fixed-price RFQ for repair of an 8" water main ("up to 60 ft" replacement) and a 4" isolation valve at NAS Corpus Christi; HCS submitted a $40,975 bid and won the contract.
  • Site visit and contract language required selective excavation to expose leaking sections and replacement "as necessary"; FAR clauses for Differing Site Conditions and Changes were incorporated.
  • Contractor (HCS subcontractor Quality Contracting) excavated ~10' of the 8" main, discovered the active leak was in a 4" branch that intersected the 8" main at a tee, and excavated the 4" line to locate the leak.
  • The Navy COR directed the contractor to cap the 4" branch (added work) instead of allowing removal/replacement of the tee on the 8" main (work the contractor had planned and material for). The COR also directed an additional water-quality test.
  • After completion, the CO issued a unilateral deductive modification removing all 8" pipe replacement work and reduced the contract price by ~$21,082 (to $19,892.87), relying on a COR R.S. Means estimate; HCS appealed to the ASBCA seeking the original contract price plus adjustments for extra work.

Issues

Issue HCS's Argument Navy's Argument Held
Whether the Government may unilaterally delete performed work and reprice a firm-fixed-price contract after completion HCS: No; government cannot convert fixed-price contract into cost basis after performance; contractor is entitled to contract price unless gov't proves savings Navy: Yes; CO unilaterally deleted 8" work after discovering differing condition and may reduce price by the cost savings (using COR/Means estimate) Held for HCS: gov't failed to prove savings; cannot reprice completed work without showing net cost savings to contractor
Proper measure of credit for deleted work HCS: Credit limited to actual net savings and must be supported by evidence; contractor provided credits/receipts for materials and labor Navy: Used COR Means estimate instead of contractor records, asserting appellant failed to provide cost documentation Held: Government bears burden to prove amount of savings; Navy did not rebut contractor's unchallenged evidence of credits and extra costs
Whether the contractor performed all original contract work HCS: Performed all required work except replacement of the 8" tee portion after COR directed otherwise; performed added items (cap & water test) Navy: Argues the contract required replacement/excavation of "up to 60 ft" and thus deletion justified Held: Contract required selective replacement "as necessary"; HCS performed required work except the discrete 8" replacement the COR directed not to perform
Entitlement to adjustment for extra work (capping 4" and water test) HCS: Entitled to reimbursement for extra work; provided amounts for cap, labor, and water test Navy: Demanded receipts but did not challenge reasonableness at trial; relied on Means estimate instead Held: HCS entitled to the unchallenged extra amounts; net result is HCS recovers contract price plus $282 net upward adjustment

Key Cases Cited

  • Nager Elec. Co. v. United States, 442 F.2d 936 (Ct. Cl. 1971) (government bears burden to prove amount of cost savings from deleted work)
  • Bruce Constr. Corp. v. United States, 324 F.2d 516 (Ct. Cl. 1963) (equitable adjustment must relate to the altered position of the contractor caused by the modification)

Outcome: Appeal sustained. ASBCA awarded HCS $41,257 total (original contract $40,975 plus $282 net extra), less payments already received, plus CDA interest from date of claim.

Read the full case

Case Details

Case Name: HCS, Inc.
Court Name: Armed Services Board of Contract Appeals
Date Published: Sep 20, 2016
Docket Number: ASBCA No. 60533
Court Abbreviation: A.S.B.C.A.