History
  • No items yet
midpage
947 N.E.2d 421
Ind. Ct. App.
2011
Read the full case

Background

  • Contract for recycled concrete base for a 150x200 ft parking area; price reduced from $13,500 to $12,000.
  • Moore began work and supplied samples; Hawa paid $5,000 to start; remaining balance due on completion milestones.
  • Hawa expressed dissatisfaction with the recycled concrete and refused the second $5,000 payment, demanding more work completed or different product.
  • Bank inspection was arranged; Moore moved the power rake blender to the site; bank did not attend the inspection.
  • Moore walked off the job after five days with the blender idle; Hawa filed a breach claim in small claims court; Moore counterclaimed for payment.
  • Small claims court awarded Moore $4,745; Hawa appeals alleging error in judgment, damages, and due process.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether Moore proved repudiation due to lack of adequate assurance Hawa argues Moore failed to provide adequate assurance of payment Moore claims Hawa's repudiation allowed demand for assurance and deemed breach when not provided Repudiation found; Moore entitled to counterclaim
Whether damages were properly calculated and the duty to mitigate Hawa challenges inclusion of certain costs and argues mitigation should reduce damages Moore argues all incurred costs are recoverable within mitigation framework Damages reduced on mitigation grounds; remanded for $750 deduction; total 3,995
Whether Hawa's due process rights were violated by limited evidentiary opportunity Hawa contends he was denied opportunity to defend against counterclaim Moore asserts parties were offered reschedule or memos; Hawa declined No due process violation; proceedings conducted with offered alternatives

Key Cases Cited

  • Trinity Homes, LLC v. Fang, 848 N.E.2d 1065 (Ind.2006) (clearly erroneous standard in small claims appeals; deference to trial court)
  • Crider & Crider, Inc. v. Downen, 873 N.E.2d 1115 (Ind.Ct.App.2007) (damages and mitigation principles in contract breach)
  • Berkel & Co. Contractors, Inc. v. Palm & Assocs., Inc., 814 N.E.2d 649 (Ind.Ct.App.2004) (mitigation and damages framework in breach actions)
  • Jay Cnty. Rural Electric Membership Corp. v. Wabash Valley Power Ass'n, 692 N.E.2d 905 (Ind.Ct.App.1998) (repudiation and adequate assurances concept in non-UCC contract disputes)
Read the full case

Case Details

Case Name: Hawa v. Moore
Court Name: Indiana Court of Appeals
Date Published: Mar 29, 2011
Citations: 947 N.E.2d 421; 2011 WL 1137337; 2011 Ind. App. LEXIS 550; 87A01-1007-SC-344
Docket Number: 87A01-1007-SC-344
Court Abbreviation: Ind. Ct. App.
Log In
    Hawa v. Moore, 947 N.E.2d 421