Hartness v. Nuckles
475 S.W.3d 558
Ark.2015Background
- Owner Ashley Hartness contracted orally with Restoration Plus (Rick Nuckles) in 2007 to restore a 1968 Pontiac Firebird; Hartness supplied parts and paid over nineteen invoices in cash.
- Hartness inspected and test-drove the car during the project, retrieved the car in December 2009, later returned it once for additional repairs, then kept it and drove ~1,000 miles.
- Hartness filed suit in September 2012 asserting breach of express and implied warranty, money had and received (unjust enrichment), conversion, fraud, deceit, and false representation.
- The circuit court found warranty claims failed for lack of statutory UCC notice and rejected other claims for lack of proof; bench trial, findings reviewed for clear error on factual issues.
- The Supreme Court affirmed: held that if warranties exist in a services contract, the UCC §4-2-607 notice requirement applies; on the facts Hartness failed to give reasonable pre-suit notice.
- Court also affirmed denial of unjust enrichment (no evidence of defendant’s wrongful gain) and conversion (finder of fact credited testimony that old parts were worthless/discarded).
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether UCC notice requirement applies to breach-of-warranty claims in a services contract | Hartness: UCC notice applies only to goods, not services, so no pre-suit notice required | Nuckles: If warranties apply to services, UCC notice should apply by analogy; Hartness failed to give notice | If express or implied warranties exist for services, the UCC notice rule (Ark. Code Ann. §4-2-607) applies; Hartness failed to give reasonable notice, so warranty claims barred |
| Whether Hartness’s pre-suit communications constituted reasonable notice | Hartness: post-possession complaints and trial evidence suffice | Nuckles: No notice until complaint filed 33 months after pickup | Trial finding that first notice was the complaint (33 months later) was not clearly erroneous; unreasonable delay |
| Unjust enrichment / money had and received — entitlement and measure of recovery | Hartness: entitled to restitution; offered evidence of cost to repair to bargained-for condition | Nuckles: Plaintiff failed to show defendant’s unjustified gain; proofs were speculative | Recovery denied: unjust enrichment requires proof approximating defendant’s wrongful gain; Hartness proved repair costs (expectation), not defendant’s gain, so claim speculative |
| Conversion — retention/loss of old parts and damages | Hartness: Nuckles kept or destroyed parts and should pay for them | Nuckles: Old parts were damaged, labelled, and discarded as worthless | Trial court’s factual finding that parts were worthless/not improperly converted was not clearly erroneous; affirmed |
Key Cases Cited
- Williams v. Mozark Fire Extinguisher Co., 318 Ark. 792 (1994) (notice is condition precedent for recovery under UCC warranty provisions)
- Gwin v. Daniels, 357 Ark. 623 (2004) (appellate court will not decide issues not presented to or decided by trial court)
- Graham Const. Co. v. Earl, 362 Ark. 220 (2005) (UCC principles may guide contract-for-services analysis by analogy)
- Haase v. Starnes, 323 Ark. 263 (1996) (UCC provides guidance on contract principles by analogy)
- Cinnamon Valley Resort v. EMAC Enters., Inc., 89 Ark. App. 236 (2005) (court of appeals applied UCC-like notice requirement in construction warranty dispute)
- McQuillan v. Mercedes-Benz Credit Corp., 331 Ark. 242 (1998) (elements and nature of conversion tort)
- Sanders v. Bradley Cnty. Human Servs. Pub. Facilities Bd., 330 Ark. 675 (1997) (measure of restitution is defendant’s gain)
- El Paso Prod. Co. v. Blanchard, 371 Ark. 634 (2007) (reversal where restitution award was speculative)
