History
  • No items yet
midpage
Hartec Corp. v. GSE Associates, Inc.
91 So. 3d 375
| La. Ct. App. | 2012
Read the full case

Background

  • Hartec contracted with Waterworks to construct the Terrebonne Parish Schriever Water Plant Expansion for $4,950,000, with GSE providing architectural/engineering plans.
  • Hartec terminated the contract for cause on June 26, 2002 after suspensions exceeding 90 days on key areas, prompting litigation with Waterworks, GSE, and GSE’s insurer Continental Casualty.
  • Bifurcated trial under La. R.S. 13:5105 separated claims against private vs public entities, with a jury deciding Hartec’s claims against GSE and Waterworks’ claims against Hartec/GSE, and a judge deciding the reconventional demand.
  • The jury found Hartec liable against GSE for $909,222.49, while the judge found Waterworks against Hartec for $1,555,472.69, creating inconsistent verdicts in a bifurcated trial.
  • The trial court’s combined judgment reversed, amended, and included an award to Waterworks; appellate review focused on the judge’s verdict and the extent of Hartec’s damages.
  • On appeal, the court reversed the award of liquidated damages against Hartec and awarded Hartec $45,939.49 for additional compensation, affirming the rest of the Waterworks judgment.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Standard of review for inconsistent bifurcated verdicts Hartec argues judge’s verdict should harmonize with jury findings. Waterworks argues no need to harmonize; focus on each verdict separately. Judgment reviewed de novo for the judge’s findings; no harmonization required between inconsistent verdicts.
Contract balance and liquidated damages Hartec not entitled to liquidated damages and contract balance due under delays caused by others. Waterworks contends damages and balance are due per contract terms and delays were not excusable. Trial court erred in liquidated damages; reversed to remove $479,500; contract balance otherwise affirmed.
entitlement to extra compensation for specific extra work Hartec deserves payment for RCP elevational clash, raw water pipe rework, and roadway repair. GSE/Waterworks argued costs were due to Hartec’s own fault or plan issues. Award $45,939.49 for specified items; other claimed items not awarded.
Delay damages Waterworks engineer delays and floods caused Hartec’s additional delays warrant time extensions and damages. Delays not properly proven or excused beyond extensions already granted. No additional delay damages beyond already awarded extensions; court's ruling affirmed on this point.
Adequacy of GSE’s plans and overall project costs Plans inadequately protected Hartec from concrete leaks and pipe issues; costs were reasonably incurred. Plans adequate; damages largely due to Hartec’s construction practices. Trial court findings on plan adequacy and project completion costs largely affirmed; manifest error not shown.

Key Cases Cited

  • Rosell v. ESCO, 549 So.2d 840 (La. 1989) (great deference to trial-finder when credibility issues exist)
  • Thornton v. Moran, 348 So.2d 79 (La.App. 1 Cir. 1977) (more reasonable standard harmonizing verdicts)
  • Cornish v. State Dept. of Transp. & Dev., 647 So.2d 1170 (La. App. 1 Cir. 1994) (allocations of fault and harmonization guidance)
  • Eppinette v. City of Monroe, 698 So.2d 658 (La. App. 2 Cir. 1997) (manifest error then more reasonable standard with mixed damages)
  • Deville v. Town of Bunkie, 364 So.2d 1378 (La. App. 3 Cir. 1978) (adopted the more reasonable standard for some time)
  • Hebert v. Rapides Parish Police Jury, 934 So.2d 912 (La. App. 3 Cir. 2006) (de novo standard adopted for bifurcated trial review)
  • McDaniel v. Carencro Lions Club, 934 So.2d 945 (La. App. 3 Cir. 2006) (four-part harmonization approach critique of mixed standards)
  • Aubert v. Charity Hospital of Louisiana, 363 So.2d 1223 (La. App. 4 Cir. 1978) (illustrative of appellate review in complex mixed-verdict cases)
  • American Casualty Co. v. Ill. Central Gulf R.R., 601 So.2d 712 (La. App. 5 Cir.) (adoption of more reasonable standard in fault allocations)
  • Stobart v. State, DOTD, 617 So.2d 880 (La. 1993) (manifest error standard for appellate review of factual findings)
Read the full case

Case Details

Case Name: Hartec Corp. v. GSE Associates, Inc.
Court Name: Louisiana Court of Appeal
Date Published: Feb 24, 2012
Citation: 91 So. 3d 375
Docket Number: No. 2010 CA 1332
Court Abbreviation: La. Ct. App.