History
  • No items yet
midpage
Hap Taylor & Sons, Inc. v. Summerwind Partners, LLC
338 P.3d 1204
Idaho
2014
Read the full case

Background

  • Summer Wind at Orchard Hills: multi-use development (residential lots + golf course) developed by Union Land; plats recorded Feb 2, 2007.
  • Knife River (subcontractor to ELL) performed paving beginning Aug 22, 2006; later did golf cart paths after an August 2007 change order; recorded materialmen’s liens Oct 25, 2007 for $217,385.82.
  • Stanley Consulting contracted June 18, 2007 to provide engineering services; performed some off-site/project-administration work before IFA recorded a $9.5M deed of trust on July 13, 2007, but first performed on-site work July 19, 2007; Stanley filed to establish priority of an engineer’s lien.
  • IFA (lender) foreclosed its deeds of trust (2009); disputes over lien priorities led to consolidated litigation: Stanley appealed district court’s ruling on engineer’s lien priority; IFA cross-appealed district court’s grant of summary judgment to Knife River.
  • District court held (1) engineer’s lien priority relates back only to first on-site physical work; (2) Knife River’s lien for roadways and cart paths was valid and superior to IFA’s deed of trust without separate designation. Court of Appeals vacated and remanded.

Issues

Issue Plaintiff's Argument (Stanley/IFA) Defendant's Argument (IFA/Knife River) Held
1) When does an engineer’s lien priority relate back under I.C. §45-506? Stanley: priority dates to when engineer commenced any authorized professional services under contract (including off-site). IFA: “commenced to be furnished” requires on-site delivery/physical furnishing, not mere off-site preparation. Court: Vacated district court; holds priority dates to when engineer commenced furnishing authorized professional services under contract (off-site work counts). Remand for further proceedings.
2) Did Knife River need separate liens for roadways and cart paths (two contracts)? IFA: Roadways and cart paths were under separate contracts; Knife River’s roadway lien may be untimely if separate. Knife River: Single unit-price proposal covered all paving (roadways + cart paths). Court: Proposal ambiguous; genuine fact issues exist about scope and contract multiplicity. Summary judgment for Knife River reversed; remand for findings.
3) Do roadways/cart paths qualify as "improvements" under I.C. §45-508 such that amounts must be designated? IFA: Roadways and cart paths are structures/improvements; separate improvements require designation on claim of lien. Knife River: Surfacing work is land improvement (not §45-508 structures) or all part of single improvement. Court: Roadways and cart paths are structures (thus "improvements" under §45-508). Court remands to determine whether they are separate improvements; if separate, designation requirement applies.
4) Must court take evidence on amount of land necessary for convenient use under I.C. §45-505 before foreclosure? IFA: District court should have taken evidence to determine land area subject to lien before decree of foreclosure. Knife River: Liens are for constructing improvements and district court did not need separate §45-505 proceeding. Court: Because roads/cart paths are structures under §45-501, §45-505 applies; district court must take evidence on land necessary for convenient use on remand.

Key Cases Cited

  • Walker v. Lytton Savings, 2 Cal.3d 152 (1970) (California mechanic’s lien statute case relied on by district court but distinguished here)
  • Beall Pipe & Tank Corp. v. Tumac Intermountain, Inc., 108 Idaho 487 (Ct. App. 1985) (interpreting “commenced to be furnished” for materialmen as delivery on-site)
  • Ultrawall, Inc. v. Wash. Mut. Bank, 135 Idaho 832 (2001) (discussed but found not directly instructive on when professional services "commence to be furnished")
  • Credit Suisse AG v. Teufel Nursery, Inc., 156 Idaho 189 (2014) (guidance on whether one continuous contract governs work for lien timing)
  • Hopkins Nw. Fund, LLC v. Landscapes Unlimited, LLC, 151 Idaho 740 (2011) (treatment of what constitutes an "improvement" and when §45-508 applies)
  • Valley Lumber & Mfg. Co. v. Driessel, 13 Idaho 662 (1907) (material on separate contracts and constructive/actual notice to subcontractor)
Read the full case

Case Details

Case Name: Hap Taylor & Sons, Inc. v. Summerwind Partners, LLC
Court Name: Idaho Supreme Court
Date Published: Nov 13, 2014
Citation: 338 P.3d 1204
Docket Number: No. 40514
Court Abbreviation: Idaho