History
  • No items yet
midpage
HANDLE CONST. CO., INC. v. Norcon, Inc.
2011 Alas. LEXIS 115
Alaska
2011
Read the full case

Background

  • Norcon solicited a bid from Handle for concrete work on the Fort Greely project; Norcon provided drawings and a bid schedule; Stoops assigned estimating to Michael, who did not receive the email with attachments.
  • The drawings indicated double-pier L2 foundations; the bid schedule contemplated single-pier units, creating a discrepancy between documents.
  • Handle submitted a bid based on the schedule and drawings and was awarded the subcontract; work commenced September 15, 2008 and was completed to Norcon's satisfaction.
  • Handle later discovered, in October 2008, a discrepancy between the bid schedule and drawings and sought a change order totaling about $139,648; Norcon refused.
  • In February 2009 Handle sued for damages associated with the bid error and related delays; Norcon moved for partial summary judgment on the damages, which the superior court granted.
  • The superior court held Handle committed a unilateral mistake, allocated the risk to Handle, and entered final judgment for Norcon; Handle appealed challenging waiver and the unilateral-mistake ruling.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Waiver of implied warranty claim Handle argues implied warranty of adequate specifications. Norcon contends claim is waived; plans not in record. Waived; plans not in record and warranty theory not applicable.
Unilateral mistake and risk allocation Handle contends unilateral mistake applies and risk not properly allocated to Handle. Norcon argues proper application of unilateral-mistake theory and risk allocated to Handle. Superior court's unilateral-mistake ruling affirmed; Handle bore the risk of mistake.
August 19, 2008 email's effect on contract terms Email created ambiguities; should determine bid interpretation. Email is extrinsic context; contract interpretation permitted without ambiguity finding. Court used email to interpret terms; no reversible error in not incorporating email into contract.
Duty to inquire given large bid gap Norcon should have inquired due to 35% bid gap. No duty to inquire; risk of mistake allocated to Handle. No duty to inquire; Handle bore the risk of mistake under Restatement §154.

Key Cases Cited

  • Northern Corp. v. Chugach Electric Ass'n, 523 P.2d 1243 (Alaska 1974) (implied warranty when defective specifications render performance possible or impossible)
  • Chugach Electric Ass'n v. Northern, 523 P.2d 1243 (Alaska 1974) (design/specification defect affecting performance)
  • L.K. Comstock & Co. v. United Engineers & Constructors Inc., 880 F.2d 226 (9th Cir. 1989) (Spearin-like doctrine and implied warranty context)
  • Stuyvesant Dredging Co. v. United States, 834 F.2d 1576 (Fed. Cir. 1987) (design vs. performance specifications distinction)
  • AAB Joint Venture v. United States, 75 Fed. Cl. 414 (Fed. Cl. 2007) (examples of defective specifications and related contract considerations)
  • Kingik v. State, Dep't of Admin., Div. of Retirement & Benefits, 239 P.3d 1243 (Alaska 2010) (Restatement-based approach to contract interpretation and mistake)
  • Wasser & Winters Co. v. Ritchie Bros. Auctioneers (America), Inc., 185 P.3d 73 (Alaska 2008) (burden of proof and related contract principles in Alaska)
Read the full case

Case Details

Case Name: HANDLE CONST. CO., INC. v. Norcon, Inc.
Court Name: Alaska Supreme Court
Date Published: Oct 28, 2011
Citation: 2011 Alas. LEXIS 115
Docket Number: S-13885
Court Abbreviation: Alaska