History
  • No items yet
midpage
Hale v. Big H Construction, Inc.
288 P.3d 1046
Utah Ct. App.
2012
Read the full case

Background

  • Hales hired Big H to construct two cost-plus custom homes with a 10% builder’s fee and paid many subcontractors directly.
  • Big H filed a $165,000 mechanics’ lien on Lot 45; Hale sued for breach of contract and Big H counterclaimed for nonpayment.
  • The project involved 47 subcontractors; some costs were paid directly by the Hales; tensions led Big H to leave the job in 2004.
  • Court-ordered damages: Big H awarded $172,100 builder’s fee, $94,463 prejudgment interest, and $342,240.84 in attorney fees and costs; new-trial motions denied.
  • Trial court relied on Big H’s invoices, a cost-tracking spreadsheet, and expert testimony; Hale credibility findings undermined Hale and expert witnesses.
  • Court acknowledged potential clerical error in a separate minute entry but did not alter final judgment; Hale appealed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the damages were properly calculated from costs incurred Hales argue damages should be based only on actual expenditures, not estimates Big H relied on invoices, payment records, and cost estimates per Traco No reversible error; costs may be proved with documentary evidence and reasonable estimates per Traco.
Whether inclusion of land cost in the builder’s fee violated the Act Cost of Lot 45 cannot be part of a builder’s fee under the Licensing Act Cost of land was a cost, not a real estate commission; fee based on costs plus 10% Not reversible; issue inadequately briefed or waived under rule 8(c).
Whether Hale is entitled to an offset for unfinished punch-list items Punch-list repairs valued >$73,000 should offset the award Trial court found substantial compliance and unreliable expert estimates; no offset No reversible error; no clear error in findings of substantial completion.
Whether James Horsley had actual or apparent authority to accept $30,000 Hales paid James Horsley; argued he had authority to receive builder’s fee Trial court found no actual or apparent authority; James Horsley used funds for personal venture No reversible error; authority findings supported by record.
Whether Big H violated the Mechanics’ Lien statute Lien was inflated beyond amount due; abuse of lien right Lien reflected amounts due and court weighed evidence; no abuse Lien valid; no abuse of lien; mechanics’ lien claim affirmed.

Key Cases Cited

  • Traco Steel Erectors, Inc. v. Comtrol, Inc., 2009 UT 81 (Utah 2009) (damages evidence may include estimates if supported by documentation)
  • Wasatch Oil & Gas, LLC v. Reott, 2011 UT App 152 (Utah Ct. App. 2011) (measure of damages not at issue; context for damages formula)
  • Sachs v. Lesser, 2008 UT 87 (Utah 2008) (statutory interpretation of real estate commissions)
  • ProMax Dev. Corp. v. Mattson, 943 P.2d 247 (Utah Ct. App. 1997) (standard for reviewing trial court findings on appeal)
Read the full case

Case Details

Case Name: Hale v. Big H Construction, Inc.
Court Name: Court of Appeals of Utah
Date Published: Oct 12, 2012
Citation: 288 P.3d 1046
Docket Number: 20100785-CA
Court Abbreviation: Utah Ct. App.