History
  • No items yet
midpage
503 P.3d 1177
Okla.
2021
Read the full case

Background

  • Wynnewood (owner) contracted with WSP (prime) for environmental work; WSP subcontracted with Techsas; Techsas subcontracted with H2K to supply materials/labor.
  • The WSP–Techsas subcontract contained a lien-waiver clause and required Techsas to flow it down to its subs; H2K’s subcontract did not contain a similar waiver.
  • Techsas filed bankruptcy after receiving some payments; H2K was unpaid, served a preliminary lien notice, and filed a materialmen’s lien and foreclosure action.
  • WSP and its surety posted a bond to discharge the lien and were substituted as defendants; the trial court granted summary judgment for defendants, holding the subcontract waiver barred H2K’s lien.
  • H2K appealed, arguing (1) a subcontractor’s waiver cannot bind a non‑party materialman, and (2) 15 O.S. §821(B)(2) renders such waiver provisions void as against public policy. The Oklahoma Supreme Court retained the appeal.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Does a lien‑waiver in a subcontract bind a non‑party materialman (H2K)? H2K: No — third parties cannot be stripped of statutory lien rights by a contract they did not sign. WSP: Yes — subcontractor is charged with notice of the original contract and waiver "flows down," so H2K can claim no greater rights than Techsas. Waiver in Techsas–WSP subcontract does not automatically bind H2K; absent H2K’s own waiver, it may assert a statutory lien (remand for further proceedings).
Does 15 O.S. §821(B)(2) (public policy) invalidate lien waivers affecting mechanics’/materialmen’s liens? H2K: §821(B)(2) voids contract clauses that disallow or alter rights under the Act — it should apply and make such waivers unenforceable. WSP: §821(B)(2) does not govern mechanics’/materialmen’s liens (located in title 42); it does not control this dispute. §821(B)(2) addresses the payment/suspension/resumption statutory scheme in title 15 and does not clearly apply to title 42 lien rights; it does not render mechanics’/materialmen’s lien waivers per se invalid.
Is the choice‑of‑law clause (New York law) in the subcontract enforceable? H2K: The New York choice‑of‑law provision is void as against Oklahoma public policy. WSP: (relied on the subcontract but trial court struck choice‑of‑law). The trial court correctly held the foreign‑law provision void under 15 O.S. §821(B)(1); Oklahoma law governs.
Did the trial court properly grant summary judgment based on the subcontract waiver? H2K: No — factual development and discovery needed; waiver cannot bind non‑party. WSP: Yes — waiver barred H2K as a matter of law. Court reversed summary judgment and remanded so parties can pursue discovery and trial as necessary.

Key Cases Cited

  • Consolidated Cut Stone Co. v. Seidenbach, 75 P.2d 442 (Okla. 1937) (interpreting "to the same extent" language as limiting owner’s liability under subcontractor liens).
  • Thacher v. Int'l Supply Co., 54 P.2d 376 (Okla. 1936) (refusing to allow contracting parties to extinguish statutory rights of non‑parties).
  • Hudson‑Houston Lumber Co. v. Parks, 215 P. 1072 (Okla. 1923) (discussing subcontractors being charged with notice of the original contract).
  • Treece v. Carpenter, 222 P. 230 (Okla. 1923) (describing subcontractor lien rights as "to the same extent" as the original contractor).
  • Riffe Petroleum Co. v. Great Nat. Corp., Inc., 614 P.2d 576 (Okla. 1980) (statutory liens are in derogation of common law and must be confined to statutory terms).
  • Biantrav Contractor, LLC v. Condren, 489 P.3d 522 (Okla. 2020) (mechanics’/materialmen’s lien purpose—protecting subcontractors and securing payment).
Read the full case

Case Details

Case Name: H2K TECHNOLOGIES v. WSP USA
Court Name: Supreme Court of Oklahoma
Date Published: Nov 16, 2021
Citations: 503 P.3d 1177; 2021 OK 59
Court Abbreviation: Okla.
Log In
    H2K TECHNOLOGIES v. WSP USA, 503 P.3d 1177