History
  • No items yet
midpage

Background

  • Wynnewood owned an oil refinery; WSP (original contractor) contracted to perform environmental work and subcontracted portions to Techsas in Aug. 2018.
  • Techsas's subcontract with WSP included a lien-waiver clause and required Techsas to flow-down a similar waiver to its subs.
  • H2K contracted with Techsas in 2019 to supply materials/services; Techsas later filed bankruptcy and did not pay H2K.
  • H2K served a preliminary notice and filed a materialmen's lien (May 2019) and later sued to foreclose; WSP and its surety posted a bond to discharge the lien.
  • Trial court granted summary judgment for defendants, holding H2K was bound by Techsas’s lien waiver and the bond was exonerated.
  • Oklahoma Supreme Court retained the appeal, reversed the summary judgment, and remanded: it held the subcontract waiver did not automatically bind a nonparty materialman and §821(B)(2) did not invalidate mechanics’ liens.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether a subcontract lien-waiver binds a nonparty materialman H2K: Techsas cannot waive H2K's statutory lien rights without H2K's assent WSP: §143 makes materialman's lien "to the same extent" as subcontractor; H2K had constructive notice and is bound by the waiver The waiver in the subcontract does not automatically flow down to a nonparty materialman; H2K was not barred as a matter of law from filing a lien
Whether 15 O.S. §821(B)(2) makes lien waivers generally void as public policy H2K: §821(B)(2) voids contract terms that disallow enforcement of rights under the act, so lien-waivers are invalid WSP: §821(B)(2) governs a separate construction-payment act and should not affect mechanics' lien statutes §821(B)(2) applies to the payment/suspension/resumption act (15 O.S. §§820–821) and does not clearly reach mechanics' and materialmen's liens in title 42; it therefore does not invalidate such liens here

Key Cases Cited

  • Consolidated Cut Stone Co. v. Seidenbach, 75 P.2d 442 (1937) (interpreting "to the same extent" language as limiting owner’s liability to original contract amount)
  • Treece v. Carpenter, 222 P. 230 (1923) (describing subcontractor lien rights as "to the same extent" as contractor)
  • Hudson-Houston Lumber Co. v. Parks, 215 P. 1072 (1923) (stating subcontractor rights are controlled by original contract; cited for notice principle)
  • Thacher v. Int'l Supply Co., 54 P.2d 376 (1936) (rejecting contract terms that extinguish statutory rights of nonparties)
  • Riffe Petroleum Co. v. Great Nat. Corp., Inc., 614 P.2d 576 (1980) (statutory liens are in derogation of common law and must be confined to statutory terms)
Read the full case