955 F.3d 1001
D.C. Cir.2020Background
- Gulf South filed a Section 7 application to construct the Westlake Expansion (compressor station + short pipeline) to serve a new Entergy Louisiana power plant; Entergy executed a 20‑year precedent agreement for all expansion capacity.
- Gulf South proposed "incremental‑plus" (additive) rates: any shipper using the new facilities would pay the existing Lake Charles Zone rate plus an incremental Westlake Expansion rate reflecting construction cost.
- FERC approved the certificate but rejected Gulf South’s incremental‑plus proposal; it made Entergy (the expansion shipper) pay a higher incremental rate while existing Lake Charles shippers pay only the lower zone rate even when they occasionally use the expansion facilities. The rates diverged sharply ($0.1325 vs $0.03 per dekatherm).
- FERC also denied Gulf South’s proposed depreciation rate based on a 35‑year useful life (Gulf South asked 2.86%) and denied a revised initial rate of return (Gulf South sought ~10.8%; FERC retained the company’s last approved 10.41%).
- Gulf South sought rehearing and then judicial review, challenging FERC’s denial of incremental‑plus rates and its decisions on depreciation and initial rate of return.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether FERC permissibly denied Gulf South’s requested incremental‑plus (additive) rates for use of the expansion facilities | Gulf South: incremental‑plus rates are appropriate because the pipeline can track which shippers use the expansion; cost‑causation dictates users of the expensive expansion should pay the expansion cost; alternatively, create a new rate zone | FERC: facilities are part of an integrated system so incremental‑plus is inappropriate; existing shippers already pay for zone facilities; policy favors charging only expansion subscribers; open‑access/secondary service makes treatment reasonable | Court: Vacated denial as arbitrary and capricious. Substantial evidence supports FERC’s integration finding, but FERC failed to explain why integration justified denying incremental‑plus rates when use can be tracked; remanded for further explanation and consideration of a new rate zone |
| Whether FERC erred in refusing to update Gulf South’s initial rate of return in the Section 7 order | Gulf South: recent changes in capital structure justify updating the rate of return now (to ~10.81/10.68%) | FERC: longstanding policy is to use the last approved rate of return in Section 7 proceedings and defer any update to a full Section 4 rate case (with evidentiary hearing) | Court: Denial upheld. FERC reasonably applied its policy and permissibly required a Section 4 hearing to address fact‑intensive issues; Gulf South’s settlement choices and moratorium contributed to the status quo |
| Whether FERC erred in rejecting Gulf South’s proposed depreciation rate based on a 35‑year useful life | Gulf South: expansion life justifies higher depreciation (2.86%); contract life with Entergy supports a shorter useful life | FERC: general Section 7 practice is to use the last approved depreciation rate for integrated expansions unless a clear single‑customer/lateral exception applies | Court: Denial upheld. Gulf South conceded that the 20‑year contract life was not the correct benchmark and failed to justify the 35‑year figure in the record; using the last approved 1.32% rate was reasonable |
Key Cases Cited
- Atl. Ref. Co. v. Pub. Serv. Comm’n of State of N.Y., 360 U.S. 378 (Sup. Ct.) (Section 7 rates "hold the line" pending full Section 4 adjudication)
- Battle Creek Gas Co. v. Fed. Power Comm’n, 281 F.2d 42 (D.C. Cir. 1960) (concept of integrated pipeline systems)
- Chippewa & Flambeau Imp. Co. v. FERC, 325 F.3d 353 (D.C. Cir. 2003) (substantial‑evidence review of FERC factual findings)
- Fla. Mun. Power Agency v. FERC, 315 F.3d 362 (D.C. Cir. 2003) (deference to agency factual findings)
- BNP Paribas Energy Trading GP v. FERC, 743 F.3d 264 (D.C. Cir. 2014) (cost‑causation principle: rates should reflect burdens/benefits)
- Ala. Elec. Co‑op., Inc. v. FERC, 684 F.2d 20 (D.C. Cir. 1982) (properly designed rates should match costs to customers)
- Carnegie Nat. Gas Co. v. FERC, 968 F.2d 1291 (D.C. Cir. 1992) (agency may depart from cost‑causation only for competing policies in limited circumstances)
- ANR Storage Co. v. FERC, 904 F.3d 1020 (D.C. Cir. 2018) (agency must justify adverse treatment relative to similarly situated competitors)
- W. Deptford Energy, LLC v. FERC, 766 F.3d 10 (D.C. Cir. 2014) (reasoned explanation required when departing from precedent)
- Fed. Power Comm’n v. Hope, 320 U.S. 591 (Sup. Ct.) (rate reasonableness principle)
- Missouri Pub. Serv. Comm’n v. FERC, 601 F.3d 581 (D.C. Cir. 2010) (need for particularized inquiry before including certain premiums in Section 7 rates)
- United Gas Imp. Co. v. Callery Props., 382 U.S. 223 (Sup. Ct.) (Section 7 rates intended as interim pending full rate adjudication)
- Petal Gas Storage, LLC v. FERC, 496 F.3d 695 (D.C. Cir. 2007) (depreciation: forecast useful life based on wear and exhaustion)
- Memphis Light, Gas & Water Div. v. Fed. Power Comm’n, 504 F.2d 225 (D.C. Cir. 1974) (depreciation increases prices to current consumers; definition of depreciation)
- Boston Edison Co. v. FERC, 885 F.2d 962 (1st Cir. 1989) (discounted cash flow method context for rate‑of‑return determinations)
