History
  • No items yet
midpage
Gulf Liquids New River Project, LLC v. Gulsby Engineering, Inc.
356 S.W.3d 54
| Tex. App. | 2011
Read the full case

Background

  • Gulf Liquids hired Gulsby as the general contractor to build two EPC Base Project plants; contracts 1 and 2 set fixed prices of $13.5M and $29M respectively.
  • NAICO issued payment and performance bonds for Gulsby; Bank of Montreal and Winterthur insured and benefited from the bonds.
  • A later $12M change order expanded the Base Project; Motiva Project and GBPP (Gulsby-Bay Plant Partners) were formed to build Motiva facilities, leading to contracts 3 and 4 with fixed fees for GBPP.
  • By 2000–2001, Gulf Liquids faced cash-flow issues; Gulf Liquids paid $4M on Milestone payments to Gulsby despite GBPP’s entitlement, creating liens and subcontractor disputes; Gulf Liquids terminated the Base Project contracts for cause in Sept. 2001 and then formally; GBPP abandoned Motiva work.
  • A lengthy jury trial awarded tort, contract, and punitive damages to Gulsby, GBPP, NAICO, and Bay; Gulf Liquids and Williams challenged those findings and the damages, leading to post-trial JNOV on tort/punitive issues.
  • On appeal, the court reversed/modified several portions: held that Gulsby’s proof of paying subcontractors was a covenant, not a condition precedent; concluded termination-for-convenience limited contractual damages; and reversed/ remanded breach-of-contract and quantum-meruit damages, while upholding dismissal of tort claims and related punitive damages.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Breach of contract via nonpayment Gulsby argues Gulf Liquids breached by withholding payment per Contracts 1–2. Gulf Liquids contends payment terms contained conditions precedent and termination rights negate breach. Breach found; covenant, not condition; but damages limited by termination clause.
Effect of termination-for-convenience on damages Gulsby seeks full contract damages for breach despite termination. Gulf Liquids argues damages are capped by the termination-for-convenience clause. Damages limited to clause limits; benefit-of-the-bargain damages not recoverable; pre-termination extra work preserved.
Quantum meruit recovery when contract exists Gulsby asserts quantum meruit can recover for extra-work or partial performance. Contract governs; no quantum meruit if work is covered or properly classified as extra work. Quantum meruit awarded to Gulsby reversed; no recovery on quantum meruit for Gulf Liquids.
Construction contract nuances for extra work Gulsby contends extra-work damages should cover pre-termination approved work. With termination, only certain pre-termination extra-work damages survive per contract terms. Extra-work damages preserved; pre-termination amounts may be recovered; and related questions remanded for proper calculation.
Fraud/tort claims tied to bonds and inter-party interference Gulsby asserts fraud and tortious interference by Gulf Liquids/Williams; seeks punitive damages. JNOV should dismiss tort findings where underlying torts are not proven or justified. Judgment for tort claims and punitive damages largely disallowed; court upheld JNOV on tort claims; punitive damages not supported.

Key Cases Cited

  • Hohenberg Bros. Co. v. George E. Gibbons & Co., 537 S.W.2d 1 (Tex. 1976) (conditions precedent to performance distinguished by contract as a whole)
  • Deerfield Ltd. P'ship v. Henry Bldg., Inc., 41 S.W.3d 259 (Tex.App.-San Antonio 2001) (ambiguous contract provisions; interpret as covenant where appropriate)
  • Solar Applications Eng'g, Inc. v. T.A. Operating Corp., 327 S.W.3d 104 (Tex. 2010) (clear language is needed to treat lien releases as conditions precedent)
  • City of Baytown v. Bayshore Constructors, Inc., 615 S.W.2d 792 (Tex. Civ. App.-Houston [1st Dist.] 1980) (contractual breach can void procedural change-order rights)
  • Schlumberger Tech. Corp. v. Swanson, 959 S.W.2d 171 (Tex. 1997) (merger/disclaimer of reliance requires careful contract-based analysis)
  • Forest Oil Corp. v. McAllen, 268 S.W.3d 51 (Tex. 2008) (waivers of reliance must be clearly expressed; contract totality matters)
  • Truly v. Austin, 744 S.W.2d 934 (Tex. 1988) (quantum meruit exception for construction contracts when not fully covered by contract)
Read the full case

Case Details

Case Name: Gulf Liquids New River Project, LLC v. Gulsby Engineering, Inc.
Court Name: Court of Appeals of Texas
Date Published: Nov 10, 2011
Citation: 356 S.W.3d 54
Docket Number: 01-08-00311-CV
Court Abbreviation: Tex. App.