History
  • No items yet
midpage
GTP Structures I, LLC v. Wisper II, LLC
153 F. Supp. 3d 983
W.D. Tenn.
2015
Read the full case

Background

  • GTP Structures I, LLC (lessor) owns MLAs/SLAs for space on cell towers; Wisper II (lessee) assumed those leases through a bankruptcy Plan and consent order.
  • MLAs: 25-year master leases with 5-year initial SLA terms, automatic five-year extensions; rent starts at $1,000 and increases 3% annually.
  • MLA notice provision required written default notice by certified mail or commercial courier and a 15-day monetary cure period before pursuing remedies.
  • Wisper II stopped paying rent beginning May 2014; GTP’s counsel emailed Wisper II’s manager repeatedly about defaults (June–Oct 2014) but did not use certified mail or courier.
  • GTP filed suit for breach of contract and unjust enrichment on Nov 25, 2014; parties cross-moved for summary judgment.
  • Bankruptcy Plan/consent order required cure of defaults and identified cure costs (court referenced $552,170), undermining Wisper II’s contention of a $300,000 cap.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Compliance with contractual notice condition precedent GTP substantially complied via emailed written notices and waited >15 days before suit Wisper II: GTP failed to use required certified mail/courier and did not specify the 15‑day cure period Court: GTP substantially complied; actual notice was given, no prejudice shown → summary judgment for GTP on breach claim
Unjust enrichment claim GTP seeks recovery in the alternative Wisper II: unjust enrichment barred because express contract exists Court: unjust enrichment claim dismissed (express contract controls)
Whether Wisper II's liability is capped at $300,000 per bankruptcy Plan GTP: Plan/consent order imposed cure obligations larger than $300,000 Wisper II: Plan exhibit lists $300,000 amount suggesting cap Court: liability not capped; consent order and bankruptcy law require assumption of executory contracts in full and cure of defaults (consent order recites ~$552,170)
Mitigation of damages GTP: no duty to mitigate because contract is non‑exclusive; nonetheless marketed tower space reasonably Wisper II: GTP failed to mitigate and factual dispute exists Court: contract non‑exclusive; GTP had no duty to minimize losses and its mitigation efforts were reasonable → no genuine issue as to mitigation; parties to brief damages amount

Key Cases Cited

  • Ondo v. City of Cleveland, 795 F.3d 597 (6th Cir. 2015) (summary judgment standard and viewing evidence in light most favorable to nonmoving party)
  • Celotex Corp. v. Catrett, 477 U.S. 317 (1986) (movant’s initial burden on summary judgment)
  • Green Tree Servicing, LLC v. Milam, 177 So.3d 7 (Fla. Dist. Ct. App. 2015) (substantial compliance with contractual notice requirement; notice not a technical trap)
  • Gorel v. Bank of New York Mellon, 165 So.3d 44 (Fla. Dist. Ct. App. 2015) (breach of condition precedent is not a defense absent prejudice)
  • System Components Corp. v. Florida Dep’t of Transp., 14 So.3d 967 (Fla. 2009) (doctrine of avoidable consequences and limits on mitigation)
  • Cinicola v. Scharffenberger, 248 F.3d 110 (3d Cir. 2001) (executory contracts must be assumed in their entirety under § 365)
Read the full case

Case Details

Case Name: GTP Structures I, LLC v. Wisper II, LLC
Court Name: District Court, W.D. Tennessee
Date Published: Dec 22, 2015
Citation: 153 F. Supp. 3d 983
Docket Number: No. 14-1317
Court Abbreviation: W.D. Tenn.