History
  • No items yet
midpage
Gsc Construction, Inc. v. Secretary of the Army
21-1803
| Fed. Cir. | May 2, 2022
Read the full case

Background

  • GSC Construction contracted with the U.S. Army Corps of Engineers in 2011 to build two warehouses with a contract start of Sept. 26, 2012 and completion date of Feb. 3, 2014.
  • Two primary delays: (1) a dispute over responsibility for removing/overexcavating wet soil for a waffle‑mat foundation (GSC claimed Harper Construction was responsible; the Army directed GSC to perform the work; Harper later provided specialized equipment and performed the work), and (2) design/shop‑drawing delays after GSC used the 2012 Unified Facilities Criteria (UFC) instead of the required 2007 UFC; both parties missed the incorrect‑version error for weeks.
  • The Army issued notices of delinquency in Jan. and Apr. 2014 and terminated the contract for default on June 18, 2014.
  • GSC appealed to the Armed Services Board of Contract Appeals (ASBCA), claiming entitlement to a 321‑day extension, damages, and conversion of the termination to one for convenience; the ASBCA denied relief.
  • GSC appealed the ASBCA denial to the Federal Circuit, which reviewed legal issues de novo and factual findings for substantial evidence.

Issues

Issue Plaintiff's Argument (GSC) Defendant's Argument (Army) Held
Whether the Army materially breached by assigning soil removal to Harper Appendix RR and Harper specs show Harper must provide the pad "complete" so Harper was responsible for overexcavation Multiple contract provisions (GSC proposal, §§6.3.1.1(e), 6.3.1.2) make GSC responsible for site prep and select fill Held for Army: contract language and context place soil‑removal responsibility on GSC; attachment of Harper specs was "for information only"
Whether GSC was entitled to a time extension because the Army reviewed drawings under the wrong UFC version Army's negligent review of drawings under 2012 UFC (not 2007) caused delay and warrants extension GSC had contract obligations to coordinate and ensure correct design standards; FAR clause and §1.7 assign design‑coordination responsibility to GSC Held for Army: GSC used wrong UFC; contract and FAR provisions make GSC responsible for errors and coordination, so no extension
Whether the Army forfeited the original Feb. 3, 2014 completion date by allowing work to continue past that date Because Army let GSC work past Feb. 3, it forfeited right to enforce that completion date Army repeatedly reserved its rights and expressly stated it did not waive or condone delinquency Held for Army: repeated explicit reservations of rights prevented forfeiture

Key Cases Cited

  • Kellogg Brown & Root Servs., Inc. v. Sec’y of the Army, 973 F.3d 1366 (Fed. Cir. 2020) (standard of review and limits on setting aside ASBCA factual findings)
  • McDonnell Douglas Corp. v. United States, 323 F.3d 1006 (Fed. Cir. 2003) (standard for terminating a contract for default requires reasonable belief contractor unlikely to finish on time)
  • Lisbon Contractors, Inc. v. United States, 828 F.2d 759 (Fed. Cir. 1987) (same default‑termination principle cited)
  • Elec. Boat Corp. v. Sec’y of the Navy, 958 F.3d 1372 (Fed. Cir. 2020) (de novo review of legal contract interpretation, but Board’s expertise given careful consideration)
  • LAI Servs., Inc. v. Gates, 573 F.3d 1306 (Fed. Cir. 2009) (contracts must be construed to give reasonable meaning to all parts)
  • Securiforce Int’l Am., LLC v. United States, 879 F.3d 1354 (Fed. Cir. 2018) (government prior material breach can excuse contractor nonperformance)
  • Sauer Inc. v. Danzig, 224 F.3d 1340 (Fed. Cir. 2000) (excusable delays standard under FAR)
Read the full case

Case Details

Case Name: Gsc Construction, Inc. v. Secretary of the Army
Court Name: Court of Appeals for the Federal Circuit
Date Published: May 2, 2022
Docket Number: 21-1803
Court Abbreviation: Fed. Cir.