History
  • No items yet
midpage
Greg Opinski Construction, Inc. v. City of Oakdale
132 Cal. Rptr. 3d 170
Cal. Ct. App.
2011
Read the full case

Background

  • Oakdale sued by city after bench trial over a building contract with Opinski; city awarded liquidated damages for late completion, defects, prejudgment interest, and attorneys’ fees; Opinski and surety’s cross-claims were rejected; contract required change orders or engineer-issued decisions to extend time; escrow retention under Public Contract Code §22300 governed by a 150% setoff rule under §7107; appellate issues included timing extensions, interest, and disposition of escrow funds; the court remanded and reversed prejudgment interest, directing disposition of any excess escrow funds to Opinski on remand.
  • The project was to be completed in 300 days but substantial completion occurred September 30, 2005, with seven-plus months delay; retention was 10% of contract price deposited in escrow; stop notices claimed but not ultimately stated to reduce payment.
  • The trial court’s statement of decision treated delays as non-justiciable for fault due to contract procedures; it relied on Civil Code §1511 and Peter Kiewit to enforce contract procedures for time extensions.
  • The court ultimately awarded city $54,000 lateness, $3,266 defects, and $97,775 in fees, with escrow withheld; later rulings reversed prejudgment interest based on escrow dominion and remanded to determine the excess escrow funds.
  • The narrow appellate issues focus on application of §1511 as amended, and the ownership/control of escrow funds affecting prejudgment interest and final disposition.
  • The decision includes a remand instruction to determine the amount by which escrow retained funds exceed the city’s final award and to order payment of the difference to Opinski.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether liquidated damages were proper when delays were caused by the owner and not extended under contract procedures Opinski—Peter Kiewit bars damages for owner-caused delay absent timely extensions City—contract procedures must be followed to extend time; noncompliance forecloses extensions Yes, reversed/affirmed as appropriate under §1511 amendment and contract terms
Whether Civil Code §1511 as amended allows reliance on owner-caused delay despite no timely extension Opinski—owner-caused delay should excuse performance; Peter Kiewit applies City—amendment permits contract-specifc notice and decisions to excuse delays Yes, contract procedures control and preclude Peter Kiewit-based relief
Whether prejudgment interest on the city’s damages was proper given escrow retention Opinski—escrow funds cannot support prejudgment interest if held by escrow City—escrow terms show loss of dominion; interest improper No; prejudgment interest reversed
Disposition of the escrow funds after reversal of prejudgment interest Opinski—excess escrow should be released City—escrow may be used to satisfy judgment Remand to determine excess and order payment of difference to Opinski
Whether the trial court properly treated withholdings/stop notices and damages in light of escrow Opinski—stop notices do not justify withholding beyond permitted limits City—release/withholdings governed by escrow and Public Contract Code provisions Remand/affirmed to the extent consistent with escrow disposition

Key Cases Cited

  • Peter Kiewit Sons’ Co. v. Pasadena City Junior College Dist., 59 Cal.2d 241 (1963) (owner may not be bonded by notice requirements to deny damages for owner-caused delays; §1511 amended to allow contract-based notices)
  • Civil Code §1511 amendment (1965), — (1965) (expressly permits contract-provided notice to claim extensions; allocates delay risk)
  • Buckman v. Tucker, 9 Cal.2d 403 (1937) (dominion and control for prejudgment interest when money is in possessor’s hands)
  • Fassberg Construction Co. v. Housing Authority of City of Los Angeles, 152 Cal.App.4th 720 (2007) (equitable setoff; retention funds exceeding judgment must be released)
  • General Insurance Co. v. Commerce Hyatt House, 5 Cal.App.3d 460 (1970) (pre-amendment §1511 considerations; notice requirements)
  • Aetna Cas. & Surety Co. v. Bd. of Trustees, 223 Cal.App.2d 337 (1963) (pre-amendment law; contract-based delay relief)
  • Insurance Co. of North America v. Bechtel, 36 Cal.App.3d 310 (1973) (illustrative precedent on prejudgment interest/escrow)
Read the full case

Case Details

Case Name: Greg Opinski Construction, Inc. v. City of Oakdale
Court Name: California Court of Appeal
Date Published: Oct 6, 2011
Citation: 132 Cal. Rptr. 3d 170
Docket Number: Nos. F060219, F060727
Court Abbreviation: Cal. Ct. App.