History
  • No items yet
midpage
616 S.W.3d 545
Tenn. Ct. App.
2020
Read the full case

Background

  • In 2014 GCB and Neill and Diane MaGee signed a written construction contract for a custom home; the contract required the owner to notify the contractor in writing of defects and to permit the contractor a stated short period to repair (paragraph 10), and it contained a separate termination-for-default clause (paragraph 19).
  • In late July 2015 MaGee sent a punch list; on July 31 Calfee inspected and agreed to return August 3 to make corrections.
  • On August 3, 2015 MaGee told Calfee and his subcontractors they were not allowed back in the home; Calfee repeatedly offered to return (including an August 24 demand letter from counsel) but was excluded until MaGee’s counsel permissively invited corrections in November 2015.
  • A partial settlement facilitated by a mutual friend resulted in payment to GCB with $25,418.51 retained by MaGee for flooring disputes; remaining disagreement about flooring led GCB to sue in March 2016 and MaGee to counterclaim for large damages for alleged defective work.
  • The trial court initially denied, then later granted summary judgment to GCB, finding MaGee’s refusal to allow cure was a material breach; the court awarded GCB attorney’s fees (previously $62,844.96) and dismissed MaGee’s accounting request; the Court of Appeals affirmed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether GCB was entitled to summary judgment based on MaGee’s refusal to allow cure MaGee barred GCB from returning to cure punch-list items, so GCB is owed the unpaid balance MaGee asserts defects were so severe or known to the contractor that notice and opportunity to cure were excused; factual disputes exist about who first materially breached Court: Tennessee law and the contract require notice/opportunity to cure; MaGee’s unequivocal exclusion of GCB was a material breach; summary judgment for GCB affirmed
Whether MaGee’s later November 2015 allowance to have GCB return satisfied the opportunity-to-cure requirement GCB says the August exclusion prevented any reasonable opportunity to cure; later invitation after three months was not timely MaGee says he later permitted GCB to return so cure occurred Court: November reversal came too late to constitute a reasonable opportunity to cure; initial exclusion was dispositive
Whether MaGee is entitled to an accounting of funds paid to GCB GCB: parties settled non-floor issues; only flooring money remained in dispute MaGee: no formal settlement; retained contractual rights to accounting Court: record shows a partial settlement resolving non-floor claims; accounting unnecessary and dismissed
Whether GCB may recover additional attorney’s fees after the January 2019 fee award GCB: contract provides attorney’s fees for breach; requests more fees incurred after January 2019 MaGee: prior fee award was substantial and encompassed reasonable fees Court: prior award was reasonable under the circumstances; no additional fees awarded

Key Cases Cited

  • Forrest Constr. Co., LLC v. Laughlin, 337 S.W.3d 211 (Tenn. Ct. App. 2009) (excusing notice/opportunity-to-cure where contractor abandoned job and was unresponsive)
  • Carter v. Krueger, 916 S.W.2d 932 (Tenn. Ct. App. 1995) (notice and opportunity-to-cure principle in construction-defect context)
  • United Brake Sys., Inc. v. Am. Envtl. Prot., Inc., 963 S.W.2d 749 (Tenn. Ct. App. 1997) (first material breach precludes recovery for subsequent breaches)
  • McClain v. Kimbrough Constr. Co., Inc., 806 S.W.2d 194 (Tenn. Ct. App. 1990) (same rule regarding first breach)
  • Madden Phillips Constr., Inc. v. GGAT Dev. Corp., 315 S.W.3d 800 (Tenn. Ct. App. 2009) (contractual remedies and breach sequencing)
  • 84 Lumber Co. v. Smith, 356 S.W.3d 380 (Tenn. 2011) (contract interpretation is a question of law guided by the contract’s plain language)
  • Rye v. Women’s Care Ctr. of Memphis, MPLLC, 477 S.W.3d 235 (Tenn. 2015) (summary-judgment standard and the nonmoving party’s burden)
  • Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574 (U.S. 1986) (nonmoving party must present specific facts showing a genuine issue for trial)
Read the full case

Case Details

Case Name: Greg Calfee Builders LLC v. Neill Magee and Diane Magee
Court Name: Court of Appeals of Tennessee
Date Published: Jun 29, 2020
Citations: 616 S.W.3d 545; E2019-00905-COA-R3-CV
Docket Number: E2019-00905-COA-R3-CV
Court Abbreviation: Tenn. Ct. App.
Log In
    Greg Calfee Builders LLC v. Neill Magee and Diane Magee, 616 S.W.3d 545