History
  • No items yet
midpage
Great Western Drilling, Ltd. v. Pathfinder Oil & Gas, Inc. and Cathlind Energy, LLC
568 S.W.3d 148
| Tex. App. | 2017
Read the full case

Background

  • Great Western sent a June 1, 2004 letter offering Pathfinder a 25% working interest in new leases and asked for acceptance within 48 hours; Pathfinder signed and returned the letter within that period.
  • The letter reserved certain conditions: Pathfinder would assume third‑party obligations (the Kennedys) and could not assign without Great Western’s written consent; a formal participation agreement/JOA and AFE were to be prepared "as soon as reasonably possible."
  • Disputes arose over the percentage (Pathfinder sought 28%), timing and content of the JOA and AFE, and assignment/consent rights; Great Western alleges it withdrew the offer after an October 28 conference call and sent a withdrawal letter the next day; Pathfinder returned signed documents and a check on October 29.
  • Great Western sued for a declaratory judgment that the June 1 letter was not enforceable; Pathfinder counterclaimed for breach and sought specific performance; the parties stipulated that if Pathfinder proved an enforceable contract and breach, its remedy would be specific performance (with accounting mechanics agreed).
  • The trial court submitted only contract and breach issues to the jury (refused Great Western’s requested question on whether Pathfinder was "ready, willing, and able" to perform); the jury found the letter enforceable and that Great Western breached; trial court ordered specific performance and awarded revenue and fees.
  • On appeal, the court reversed, holding the trial court abused its discretion by refusing to submit a jury question on Pathfinder’s readiness/willingness/ability to perform, a contested element necessary for awarding specific performance; because that error was harmful, the court rendered judgment that Pathfinder take nothing.

Issues

Issue Pathfinder's Argument Great Western's Argument Held
Whether the stipulation eliminated the need to prove readiness/willingness/ability for specific performance Stipulation limited issues to existence and breach; specific performance was the agreed remedy, so no separate proof of readiness was required Stipulation did not eliminate equitable elements; Pathfinder still had burden to prove entitlement (including readiness/willingness/ability) Stipulation did not obviate the readiness/willingness/ability requirement; Pathfinder still had to prove entitlement to equitable relief
Whether the trial court erred by refusing a jury question on readiness/willingness/ability The element was unnecessary under the stipulation The element was contested factually and should have been submitted to the jury Trial court abused discretion by failing to submit the question because evidence raised a fact issue
Whether Pathfinder proved it was ready, willing, and able to perform (financial ability to meet AFE/drilling costs) Pathfinder pointed to returning signed AFE/JOA and payment of $9,968.98 and argued it was prepared to proceed Great Western pointed to Pathfinder’s renegotiation attempts, lack of proof of credit/escrow/line of credit, and evidence of cash shortage The record lacked conclusive proof of Pathfinder’s financial ability; fact question existed and jury should have decided it
Remedy and disposition (should court render or remand) Pathfinder argued no need for further factfinding; specific performance awarded below Great Western sought reversal because omission of jury question was harmful Court reversed and rendered judgment that Pathfinder take nothing because the case was fully developed and the error was harmful

Key Cases Cited

  • DiGiuseppe v. Lawler, 269 S.W.3d 588 (Tex. 2008) (party seeking specific performance must prove readiness, willingness, and ability to perform)
  • J.M. Davidson, Inc. v. Webster, 128 S.W.3d 223 (Tex. 2003) (contract construction: give effect to all provisions)
  • El Paso Field Servs., L.P. v. MasTec N. Am., Inc., 389 S.W.3d 802 (Tex. 2012) (clarifies when contract language is unambiguous and construed as a matter of law)
  • Italian Cowboy Partners, Ltd. v. Prudential Ins. Co. of Am., 341 S.W.3d 323 (Tex. 2011) (contract interpretation principles)
  • Coker v. Coker, 650 S.W.2d 391 (Tex. 1983) (objective: ascertain parties’ intent from the instrument)
Read the full case

Case Details

Case Name: Great Western Drilling, Ltd. v. Pathfinder Oil & Gas, Inc. and Cathlind Energy, LLC
Court Name: Court of Appeals of Texas
Date Published: Sep 29, 2017
Citation: 568 S.W.3d 148
Docket Number: 11-14-00206-CV
Court Abbreviation: Tex. App.