History
  • No items yet
midpage
Goes v. Vogler
937 N.W.2d 190
Neb.
2020
Read the full case

Background

  • Homeowners Eric and Destini Vogler contracted with Shelton Brothers (general contractor) to rebuild a house after a fire; the written contract referenced both a $282,000 "agreed upon price" and stated it was a "cost plus contract" with specified fees (warranty 2%, overhead 5%, profit 3%).
  • Contract provided initial $28,000 downpayment and monthly draws "as needed to pay for materials and services," with payments due within 10 days of draw requests; written change orders were contemplated but later the parties waived the formal requirement by conduct.
  • Work proceeded with owner-directed changes (e.g., moving a wall, added features) that increased costs and caused scheduling issues; owners became dissatisfied with progress, communications, and accounting for draws.
  • Voglers withheld full payment on a requested draw (paid only part) alleging shoddy workmanship and lack of accounting; Shelton terminated the contract and the Voglers hired another contractor to finish the house.
  • Shelton and two subcontractors (Goes Construction and Franklin Drywall) filed liens and sued for contract damages; the trial court found the contract was cost-plus, defects were punch-list items, the Voglers materially breached first by withholding payments, and entered money judgments for Shelton, Goes, and Franklin (with some allocation between Shelton and Franklin).

Issues

Issue Plaintiff's Argument (Vogler) Defendant's Argument (Shelton) Held
Contract type: fixed-price vs cost-plus The $282,000 statement shows parties intended a fixed-price contract capped at that amount Paragraph 4 expressly labels the agreement a "cost plus contract" and sets builder fees; language supports cost-plus Contract is a cost-plus agreement; appellate court affirmed trial court.
Contractor duties/accounting under cost-plus Even if cost-plus, contractor owed heightened fiduciary duties and must provide full, detailed, prompt accountings before draws and notify of overruns Contract required costs to be presented and permitted monthly draws "as needed"; no explicit fiduciary language; obligations limited to contract and law No special fiduciary duty implied as a matter of law; contractor satisfied contract accounting obligations; no breach on this basis.
Who breached first (payment suspension) Voglers justified withholding draws due to poor workmanship and lack of accounting; thus Shelton breached first Voglers unilaterally withheld required draws, breaching the contract first; workmanship issues were punch-list items Voglers committed the first material breach by suspending payments; trial court's finding affirmed.
Subsidiary lien recovery / "protected party" claim Voglers claimed they paid prime contract price and are a "protected party" so subcontractor (Goes) cannot recover more under lien statutes Payments made did not equal the prime contract price ($282,000 plus change orders); subcontractors who perfected liens remain entitled to unpaid contract balance Goes entitled to recovery ordered by trial court; "protected party" argument rejected.

Key Cases Cited

  • Grothe v. Erickson, 157 Neb. 248 (discusses definition of cost-plus contract)
  • Robison v. Madsen, 246 Neb. 22 (foreclosure of construction lien is equitable; appellate review de novo with deference to trial court factfinding)
  • Bloedorn Lumber Co. v. Nielson, 300 Neb. 722 (breach of contract actions are at law)
  • Tilt-Up Concrete v. State City/Federal, 261 Neb. 64 (contract framework applicable to construction lien disputes)
  • Forrest Const. Co., LLC v. Laughlin, 337 S.W.3d 211 (recognizes implicit duty that cost in cost-plus contract be reasonable and proper)
  • Kerner v. Gilt, 296 So. 2d 428 (discusses reasonableness requirement in cost-plus arrangements)
  • Jones v. J.H. Hiser Constr. Co., 484 A.2d 302 (contract-specific language can create a fiduciary "relationship of trust and confidence")
Read the full case

Case Details

Case Name: Goes v. Vogler
Court Name: Nebraska Supreme Court
Date Published: Jan 17, 2020
Citation: 937 N.W.2d 190
Docket Number: S-18-1201, S-18-1203
Court Abbreviation: Neb.