History
  • No items yet
midpage
122 So. 3d 487
Fla. Dist. Ct. App.
2013
Read the full case

Background

  • Global entered an oral contract with Advanced to repair Global's aircraft; dispute over amount owed led to a mechanic's lien by Advanced under Fla. Stat. ch. 713 and 329.51/713.58; Global sued for writ of replevin and damages on June 29, 2010.
  • Advanced sent a July 21, 2010 letter stating Global should withdraw its complaint within 21 days under §57.105(4); the letter did not reference a motion or indicate an enclosure.
  • Advanced served a §57.105 motion on August 12, 2010, and filed it on August 16, 2010, asserting it satisfied the twenty-one day notice requirement.
  • Global argued it was never served with a §57.105 motion under §57.105(4); the trial court relied on unsworn attorney statements that the motion accompanied the July 21 letter.
  • The trial court awarded Advanced $30,141 in attorney’s fees under §§57.105(4) and 713.29; the order was appealed as to both statutes.
  • The Florida appellate court reversed, holding no proper §57.105 notice was shown and §713.29 did not apply for a lien not within Part I Construction Liens; remanded to vacate the award.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the §57.105(4) notice requirements were satisfied. Global: no proper notice; no motion served with July 21 letter. Advanced: July 21 letter and accompanying motion satisfied notice. §57.105 not satisfied; abuse of discretion to award fees.
Whether §713.29 applies to this lien dispute. Advanced: §713.29 covers liens under this part. Statute limited to Part I Construction Liens; lien not under Part I. §713.29 does not apply; reversal on this ground.

Key Cases Cited

  • Anchor Towing, Inc. v. Fla. Dep’t of Transp., 10 So.3d 670 (Fla. 3d DCA 2009) (strict construction of §57.105(4) and requirement of a motion, not a letter)
  • Nathan v. Bates, 998 So.2d 1178 (Fla. 3d DCA 2008) (safe harbor notice regime for §57.105(4))
  • Bionetics Corp. v. Kenniasty, 69 So.3d 943 (Fla.2011) (describes safe harbor 21-day notice requirement)
  • Davidson v. Ramirez, 970 So.2d 855 (Fla. 3d DCA 2007) (illustrates last chance to withdraw frivolous claim under §57.105)
  • Daughtrey v. Daughtrey, 944 So.2d 1145 (Fla. 2d DCA 2006) (record evidence required; unsworn counsel representations insufficient)
  • Mashan Contractors, Inc. v. Bailey, 922 So.2d 330 (Fla. 3d DCA 2006) (interprets §713.29 as applying to construction liens under Part I)
  • State v. Bauman, 425 So.2d 82 (Fla. 4th DCA 1982) (evidentiary weight of attorney representations)
Read the full case

Case Details

Case Name: Global Xtreme, Inc. v. Advanced Aircraft Center, Inc.
Court Name: District Court of Appeal of Florida
Date Published: Sep 25, 2013
Citations: 122 So. 3d 487; 2013 Fla. App. LEXIS 15205; 2013 WL 5338823; No. 3D12-2220
Docket Number: No. 3D12-2220
Court Abbreviation: Fla. Dist. Ct. App.
Log In
    Global Xtreme, Inc. v. Advanced Aircraft Center, Inc., 122 So. 3d 487