History
  • No items yet
midpage
152 Conn.App. 60
Conn. App. Ct.
2014
Read the full case

Background

  • In 2007 Girolametti (owner) and Rizzo (general contractor) signed an AIA-form construction contract containing an arbitration clause governed by AAA Construction Industry Arbitration Rules.
  • A dispute arose in 2009; Rizzo filed for arbitration and Girolametti participated in 33 of 35 sessions but stopped attending the last two; the arbitrator issued an award for Rizzo on March 28, 2011.
  • Girolametti filed a court action in December 2010 seeking a declaratory judgment that the contract was void for violating professional licensing law (Rizzo allegedly performed engineering services without a license).
  • Rizzo moved to confirm the arbitration award; the trial court granted confirmation and entered judgment for Rizzo; Girolametti appealed.
  • The trial court and this court examined whether Girolametti preserved the illegality/arbitrability objection and whether his objections were timely under Connecticut arbitration statutes.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Validity of underlying contract due to alleged unlicensed engineering Girolametti: contract illegal and therefore arbitration clause unenforceable Rizzo: contract allegation does not show arbitration clause itself invalid; arbitration clause is severable Court: arbitration clause severable; plaintiff challenged contract generally, not arbitration clause specifically, so clause enforceable
Preservation of objection to arbitrability Girolametti: raised illegality at arbitration opening and through counsel; preserved issue Rizzo: plaintiff participated in arbitration and failed to properly present/press the arbitrability issue; waived objection Court: plaintiff did not refuse arbitration at outset nor clearly present the issue to arbitrator; preservation requirement not met
Timeliness of challenge to award Girolametti: untimely challenges may be excused when arbitrator lacked authority Rizzo: plaintiff’s arguments are subject to statutory timeliness rules and prior dismissal of untimely vacatur Court: MBNA exception inapplicable because plaintiff did not argue nonexistence of arbitration agreement; statutory timing applies and prior untimely vacatur confirmed
Judicial review scope of arbitral award Girolametti: court should consider illegality despite arbitration Rizzo: judicial review of awards is narrow where parties agreed to arbitrate Court: judicial review limited; arbitrator’s authority and merits decisions are final absent preserved, timely statutory grounds

Key Cases Cited

  • Zelvin v. JEM Builders, Inc., 106 Conn. App. 401 (arbitral decisions reviewed narrowly; arbitrator may decide legal and factual questions)
  • MBNA America Bank, N.A. v. Boata, 283 Conn. 381 (untimely objections are excused where no arbitration agreement existed and arbitrator lacked authority)
  • C. R. Klewin Northeast, LLC v. Bridgeport, 282 Conn. 54 (arbitration clause is severable from the contract; validity of contract presented to arbitrator)
  • Nussbaum v. Kimberly Timbers, Ltd, 271 Conn. 65 (public policy/void-contract arguments do not automatically invalidate an arbitration clause)
  • Bridgeport v. Kasper Group, Inc., 278 Conn. 466 (arbitration is informal and arbitrator has broad discretion on issues and procedure)
  • Bloomfield v. United Electrical, Radio & Machine Workers of America, 285 Conn. 278 (MBNA limited to cases where arbitrator lacked authority because no arbitration agreement existed)
  • JCV Investment Group, Inc. v. Manjoney, 56 Conn. App. 320 (party who participates in arbitration generally may waive right to judicial determination of arbitrability)
Read the full case

Case Details

Case Name: Girolametti v. Rizzo Corp.
Court Name: Connecticut Appellate Court
Date Published: Aug 5, 2014
Citations: 152 Conn.App. 60; 97 A.3d 55; AC35353
Docket Number: AC35353
Court Abbreviation: Conn. App. Ct.
Log In
    Girolametti v. Rizzo Corp., 152 Conn.App. 60