History
  • No items yet
midpage
332 Conn. 67
Conn.
2019
Read the full case

Background

  • Owners (John and Cindy Girolametti) contracted with general contractor Rizzo for a retail expansion; disputes were submitted to broad, unrestricted arbitration under an AIA-form prime contract.
  • The arbitrator found the owners defaulted by leaving the hearing and awarded Rizzo $508,597; owners later litigated claims against five subcontractors (design/construction of steel joists supporting second floor).
  • Subcontractors moved for summary judgment asserting res judicata: the owners could have raised the same claims in the arbitration with Rizzo; the trial court granted judgment for Rizzo but denied subcontractors’ motions, finding no privity.
  • The Appellate Court reversed, adopting a rebuttable presumption that subcontractors are in privity with the general contractor for purposes of res judicata when owners and the general contractor submit disputes to broad arbitration.
  • The Connecticut Supreme Court affirmed: it adopted a rebuttable presumption of privity between general contractors and subcontractors for preclusion of subsequent litigation after unrestricted arbitration, and held the record did not rebut that presumption here.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether unrestricted arbitration between owner and GC bars later suits against nonparticipating subcontractors (privity for res judicata) Presumption of privity is unfair and conflicts with precedent; subcontractors may owe independent duties that cannot be litigated in GC-owner arbitration Broad arbitration and standard contracts make GC answerable for subcontractors; arbitration awards should be presumptively final as to subcontractors to prevent multiplicity Adopted rebuttable presumption that subcontractors are in privity with GC for res judicata where owner–GC arbitration is broad and unrestricted; affirmed below
Whether privity must be shown by factual identity of claims (Wheeler reliance) Wheeler requires closer factual identity; contractual privity cannot alone support preclusion where claims differ Wheeler distinguishes transactional "same claim" element from privity; contractual privity can establish privity irrespective of factual overlap Rejected plaintiffs’ Wheeler-based argument; contractual/derivative privity is a valid basis for preclusion here
Whether the record shows intent not to treat subcontractors as within arbitration's scope Owners say project complexity and separate contracts show they did not expect arbitration to bind subcontractors Prime contract flow‑down clauses, broad arbitration clause, and owners’ litigation conduct show they should have anticipated arbitration would address subcontractor-related claims Record supports inference owners reasonably expected arbitration with Rizzo would cover subcontractor issues; presumption not rebutted
Whether arbitrator’s finding that Rizzo was not responsible for all engineering work defeats privity Owners argue the arbitrator’s statement shows Rizzo was not liable for certain subcontractor engineering, so no privity for those claims That statement reflects limited outsourcing of certain trades to contractors directly hired by owners and does not negate privity as to other subcontractor work Court interprets the arbitrator’s finding as limited and not dispositive of privity; privity still applies for claims at issue

Key Cases Cited

  • Girolametti v. Michael Horton Associates, Inc., 173 Conn. App. 630 (Conn. App. 2017) (Appellate Court decision adopting privity presumption)
  • Haynes v. Yale-New Haven Hospital, 243 Conn. 17 (Conn. 1997) (arbitration awards accorded res judicata effect)
  • Mazziotti v. Allstate Ins. Co., 240 Conn. 799 (Conn. 1997) (privity analysis focuses on functional relationships and identity of legal rights)
  • Wheeler v. Beachcroft, LLC, 320 Conn. 146 (Conn. 2016) (distinguishes same-claim and privity elements of res judicata)
  • Industrial Risk Insurers v. Hartford Steam Boiler Inspection & Ins. Co., 273 Conn. 86 (Conn. 2005) (definition of "unrestricted" arbitration)
  • DKN Holdings, LLC v. Faerber, 61 Cal. 4th 813 (Cal. 2015) (recognizes derivative liability supporting preclusion between GC and subcontractors)
  • Columbia Steel Fabricators, Inc. v. Ahlstrom Recovery, 44 F.3d 800 (9th Cir. 1995) (arbitration award for GC held res judicata as to subcontractor in privity)
Read the full case

Case Details

Case Name: Girolametti v. Michael Horton Assocs., Inc.
Court Name: Supreme Court of Connecticut
Date Published: Jun 25, 2019
Citations: 332 Conn. 67; 208 A.3d 1223; SC0034, SC20035
Docket Number: SC0034, SC20035
Court Abbreviation: Conn.
Log In
    Girolametti v. Michael Horton Assocs., Inc., 332 Conn. 67