Gadeco, LLC v. Industrial Commission
830 N.W.2d 535
| N.D. | 2013Background
- Gadeco LLC was invited to participate in the Coyote #1-32H well; the July 8, 2009 invitation described surface location, depth, and costs and stated a 30-day response deadline.
- Slawson later sent a July 15, 2009 notice changing the surface location and the estimated spud date, while asserting the completion location and costs remained substantially the same.
- Gadeco signed and paid its share of costs on August 19, 2009, but Slawson returned the check noting the 30-day election period had expired August 10, 2009.
- In November 2009, Slawson sought a risk penalty; the Commission pooled interests and imposed a 200% penalty against Gadeco as a nonparticipating owner.
- The district court reversed, and on appeal this Court reversed that reversal and remanded for findings; on remand, the Commission again found Slawson’s invitation compliant and Gadeco untimely in election.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether the invitation complied with § 43-02-03-16.3(1) (April 1, 2010). | Gadeco argues changes to location, costs, and spud date invalidated the invitation. | Slawson/Commission contend the invitation allowed flexibility and did not require a new invitation. | No; invitation satisfied the rule and changes were informational and not material. |
| Whether changes to the surface location, estimated costs, and spud date required a new invitation. | Gadeco asserts material changes necessitated a new invitation. | Commission found changes immaterial or insubstantial. | Changes were insubstantial; did not require a new invitation. |
| Whether the 30-day election deadline is mandatory. | Gadeco contends some flexibility exists; 30 days should be treated as non-mandatory. | The rule uses 'must' and is mandatory to protect cost planning. | The 30-day deadline is mandatory. |
| What standard governs appellate review of Commission findings and conclusions? | Gadeco relies on substantial evidence review. | Standard balances deference to Commission with statutory review. | Review applies the substantial-credible-evidence standard; law questions are fully reviewable. |
Key Cases Cited
- Gadeco LLC v. Industrial Comm’n, 812 N.W.2d 405 (North Dakota 2012) (principal controlling case on invitation requirements and remand for findings)
- Hystad v. Indus. Comm’n, 389 N.W.2d 590 (North Dakota 1986) (standards for deference to Commission findings on review)
- Sloan v. North Dakota Workforce Safety & Ins., 804 N.W.2d 184 (North Dakota 2011) (regulatory interpretation and standard of review guidance)
- State v. Dimmler, 456 N.W.2d 297 (North Dakota 1990) (retroactivity/controlling date considerations in regulatory analysis)
- Federal Land Bank of St Paul v. Waltz, 423 N.W.2d 799 (North Dakota 1988) (interpretation of mandatory language in regulatory provisions)
