History
  • No items yet
midpage
Frohberg Elec. Co. v. Grossenburg Implement
297 Neb. 356
Neb.
2017
Read the full case

Background

  • Owner (Grossenburg) contracted with Contractor (Kiehm) under a standard form general contract that contained a mediation-then-arbitration dispute resolution scheme in the general conditions.
  • Contractor subcontracted electrical work to Subcontractor (Frohberg); the subcontract referenced and stated the subcontractor had examined the general contract documents.
  • Subcontract contains Section 11 (to be bound by the General Contract) and Section E (under heading “The Contractor Agrees as Follows”) stating disputes between Contractor and Subcontractor "shall be settled by arbitration in the manner provided for in the General Contract."
  • A payment dispute arose; Subcontractor filed suit (including lien foreclosure) against Owner and Contractor; Owner and Contractor moved to compel arbitration.
  • District court denied the motion, reading Section E as applying only to Contractor (based on the section heading) and finding incorporation ambiguous; Owner and Contractor appealed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the subcontract unambiguously incorporated the general contract’s arbitration clause Owner/Contractor: Section E and Section 11 plainly and mutually incorporate the general contract ADR terms, so Subcontractor agreed to arbitrate Subcontractor: Section E appears under a heading for Contractor’s promises only, so it does not bind Subcontractor; incorporation is ambiguous Court: Section E’s language is unambiguous and reciprocal despite its heading; subcontractor is bound to arbitrate disputes under the general contract terms
Whether the FAA applies and relief should have been stayed pending mediation/arbitration Owner/Contractor: Subcontract is a services contract between parties of different states, so FAA governs and requires stay/compelled arbitration (mediation is a condition precedent) Subcontractor: (implicit) state-law analysis and no valid arbitration agreement applies Court: Contract involves interstate commerce (Minnesota contractor, Nebraska subcontractor); FAA applies; mediation required first and, since mediation had not occurred, the court must compel mediation then arbitration and stay the action

Key Cases Cited

  • Facilities Cost Mgmt. Group v. Otoe Cty. Sch. Dist., 291 Neb. 642 (2015) (contract-ambiguity and interpretation principles)
  • David Fiala, Ltd. v. Harrison, 290 Neb. 418 (2015) (state contract law governs formation questions; FAA equal-treatment principle)
  • Wilczewski v. Charter West Nat. Bank, 295 Neb. 254 (2016) (arbitrability is question of law on appeal)
  • Southland Corp. v. Keating, 465 U.S. 1 (1984) (FAA policy and state-law formation analysis compatibility)
Read the full case

Case Details

Case Name: Frohberg Elec. Co. v. Grossenburg Implement
Court Name: Nebraska Supreme Court
Date Published: Jul 28, 2017
Citation: 297 Neb. 356
Docket Number: S-16-987
Court Abbreviation: Neb.