History
  • No items yet
midpage
Frohberg Elec. Co. v. Grossenburg Implement
297 Neb. 356
| Neb. | 2017
Read the full case

Background

  • Owner (Grossenburg Implement, NE) contracted with Contractor (Kiehm Construction, MN) using a standard form general contract that included mediation as a condition precedent and a mandatory arbitration clause.
  • Subcontractor (Frohberg Electric, NE) entered a subcontract to perform electrical work that referenced and stated it had examined the general contract and accompanying documents.
  • Subcontract included Section 11 (agreeing to be bound by the General Contract) and Section E (under heading “The Contractor Agrees as Follows”) which stated disputes between Contractor and Subcontractor “shall be settled by arbitration in the manner provided for in the General Contract.”
  • Subcontractor filed suit and a lien for unpaid work; Owner and Contractor moved to compel arbitration based on incorporation of the general contract’s dispute-resolution process.
  • The district court denied the motion, reasoning Section E was binding only on Contractor because of its heading and that Section 11 was vague as to whether it bound Subcontractor to disputes with Owner.
  • The Nebraska Supreme Court granted review to decide whether the subcontract unambiguously incorporated the general contract’s dispute-resolution provisions and whether the FAA applied.

Issues

Issue Plaintiff's Argument (Subcontractor) Defendant's Argument (Owner/Contractor) Held
Whether the subcontract unambiguously incorporated the general contract’s ADR clauses (including mediation then arbitration) Section E’s placement under the heading “The Contractor Agrees” means Subcontractor did not agree to arbitration; Section 11 is ambiguous Section E’s text is broad and mutual in effect; Section 11 expressly binds Subcontractor to General Contract terms Court held incorporation was unambiguous: Section E and Section 11 bind Subcontractor to mediation then arbitration per the general contract
Whether the Federal Arbitration Act (FAA) governs the arbitration clause FAA does not apply or is inapplicable Subcontract is for services between parties of different states, so FAA applies Court held the subcontract involved interstate commerce; FAA governs and the arbitration agreement is enforceable, so action must be stayed pending mediation/arbitration

Key Cases Cited

  • Facilities Cost Mgmt. Group v. Otoe Cty. Sch. Dist., 291 Neb. 642, 868 N.W.2d 67 (Neb. 2015) (contract ambiguity is a question of law)
  • David Fiala, Ltd. v. Harrison, 290 Neb. 418, 860 N.W.2d 391 (Neb. 2015) (state law governs formation of arbitration agreement but must treat arbitration agreements the same as other contracts)
  • Southland Corp. v. Keating, 465 U.S. 1 (U.S. 1984) (state contract-formation rules are appropriate if they do not conflict with FAA policy)
  • CardioNet, Inc. v. CIGNA Health Corp., 751 F.3d 165 (3d Cir. 2014) (presumption of arbitrability applies only when arbitration agreement is ambiguous)
Read the full case

Case Details

Case Name: Frohberg Elec. Co. v. Grossenburg Implement
Court Name: Nebraska Supreme Court
Date Published: Jul 28, 2017
Citation: 297 Neb. 356
Docket Number: S-16-987
Court Abbreviation: Neb.