History
  • No items yet
midpage
Frohberg Elec. Co. v. Grossenburg Implement
297 Neb. 356
| Neb. | 2017
Read the full case

Background

  • Owner (Grossenburg) contracted with Contractor (Kiehm) under a standard form general contract that included mandatory mediation then arbitration for disputes.
  • Contractor subcontracted electrical work to Subcontractor (Frohberg); the subcontract referenced and stated the subcontractor had examined the general contract and made the general contract documents available.
  • Subcontract contains Section 11 (Subcontractor agrees to be bound by terms of the General Contract) and Section E (under heading “The Contractor Agrees as Follows”) stating disputes between Contractor and Subcontractor shall be settled by arbitration in the manner provided in the General Contract.
  • A payment dispute arose; Subcontractor filed a lien and sued Owner and Contractor in district court to foreclose the lien and obtain payment.
  • Owner and Contractor moved to compel arbitration under the subcontract/general contract; the district court denied the motion, finding Section E applied only to Contractor because of its heading and that Section 11 was too vague to bind Subcontractor to arbitration with Owner.
  • The Nebraska Supreme Court granted review and reversed, holding the subcontract unambiguously incorporated the general contract’s dispute resolution (mediation as a condition precedent, then arbitration) and that the FAA applied because the subcontract was between parties in different states.

Issues

Issue Plaintiff's Argument (Frohberg) Defendant's Argument (Owner/Contractor) Held
Whether the subcontract incorporated the general contract’s ADR clauses so Subcontractor must arbitrate Subcontractor argued the subcontract’s Section E and Section 11 did not bind Subcontractor to arbitration (Section E was only under Contractor heading; Section 11 was vague) Owner/Contractor argued Sections E and 11 unambiguously incorporated the general contract’s mediation/arbitration terms, binding Subcontractor Held: The subcontract unambiguously incorporated the general contract ADR provisions; Section E’s language is mutual despite heading, so disputes between Contractor and Subcontractor are subject to mediation then arbitration
Whether mediation was a condition precedent to arbitration Subcontractor contended arbitration could not be compelled because mediation was not attempted; characterization of whether mediation applied to these claims was contested Owner/Contractor argued the general conditions required mediation first and that the subcontract imported that requirement Held: The general contract’s §15.3.1 requires mediation as condition precedent; because mediation had not occurred, parties must attempt mediation before arbitration
Whether the Federal Arbitration Act (FAA) governs the arbitration clause Subcontractor argued state law should control or FAA did not apply Owner/Contractor argued FAA applied because subcontract involved interstate commerce (parties from different states) Held: FAA applies (services contract between parties in different states); arbitration agreement governed by FAA and is enforceable; district court should have stayed the action and compelled ADR per agreement
Whether the district court properly construed contract headings in limiting Section E Subcontractor relied on the document’s headings to argue Section E only bound Contractor Owner/Contractor argued headings do not override clear reciprocal language Held: Court rejected restrictive reading based on headings; plain reciprocal language controlled and headings were not determinative

Key Cases Cited

  • Facilities Cost Mgmt. Group v. Otoe Cty. Sch. Dist., 291 Neb. 642 (Neb. 2015) (contract interpretation and ambiguity are questions of law)
  • Wilczewski v. Charter West Nat. Bank, 295 Neb. 254 (Neb. 2016) (arbitrability is a question of law reviewed de novo)
  • David Fiala, Ltd. v. Harrison, 290 Neb. 418 (Neb. 2015) (state contract law governs formation of arbitration agreement unless preempted by FAA)
  • Southland Corp. v. Keating, 465 U.S. 1 (U.S. 1984) (FAA creates federal policy favoring arbitration; state rules cannot discriminate against arbitration)
  • Kindred Nursing Centers Ltd. v. Clark, 137 S. Ct. 1421 (U.S. 2017) (states must place arbitration agreements on equal footing with other contracts)
  • CardioNet, Inc. v. CIGNA Health Corp., 751 F.3d 165 (3d Cir. 2014) (federal courts apply state contract law to determine whether parties agreed to arbitrate)
  • Dasher v. RBC Bank (USA), 745 F.3d 1111 (11th Cir. 2014) (presumption of arbitrability does not apply until a valid arbitration agreement is formed)
  • Paul Revere Variable Annuity Ins. v. Kirschhofer, 226 F.3d 15 (1st Cir. 2000) (federal preference for arbitration does not resolve formation questions when ambiguity exists)
Read the full case

Case Details

Case Name: Frohberg Elec. Co. v. Grossenburg Implement
Court Name: Nebraska Supreme Court
Date Published: Jul 28, 2017
Citation: 297 Neb. 356
Docket Number: S-16-987
Court Abbreviation: Neb.