History
  • No items yet
midpage
Frohberg Elec. Co. v. Grossenburg Implement
297 Neb. 356
| Neb. | 2017
Read the full case

Background

  • Owner (Grossenburg) entered a standard-form general contract with Contractor (Kiehm) for construction in Nebraska; the general contract’s general conditions included a mandatory mediation-then-arbitration dispute-resolution scheme.
  • Contractor subcontracted electrical work to Subcontractor (Frohberg); the subcontract repeatedly referenced the general contract and stated Subcontractor had examined the general contract documents.
  • Subcontract Section 11 bound Subcontractor to the "terms of the General Contract." Section E (under the heading "The Contractor Agrees as Follows") provided that disputes between Contractor and Subcontractor "shall be settled by arbitration in the manner provided for in the General Contract."
  • A payment dispute arose; Subcontractor recorded a construction lien and sued Owner and Contractor in district court to foreclose the lien and obtain payment.
  • Owner and Contractor moved to compel arbitration under the subcontract/general contract; the district court denied the motion, reasoning the arbitration clause was not binding on Subcontractor because Section E’s placement under a Contractor-only heading made it unilateral and Section 11 was ambiguous as to applicability to Owner-Subcontractor disputes.
  • Owner and Contractor appealed; the Nebraska Supreme Court considered (1) whether the subcontract unambiguously incorporated the general contract’s dispute-resolution provisions and (2) whether the FAA applied.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the subcontract unambiguously incorporated the general contract’s arbitration procedures Frohberg (plaintiff) argued the subcontract did not bind it to the general contract ADR terms because Section E was under a Contractor-only heading and Section 11 was ambiguous Owner/Contractor argued the subcontract’s text (Section E and Section 11) plainly incorporated the general contract ADR terms and bound Subcontractor Court held the subcontract unambiguously incorporated the general contract ADR terms; Section E is mutual despite its heading and binds Subcontractor
Whether mediation is a condition precedent to arbitration under the incorporated terms Frohberg argued the ADR clause did not apply or did not require mediation first Owner/Contractor argued the general conditions require mediation as a prerequisite to binding arbitration Court held §15.3.1 of the general conditions requires mediation before arbitration; mediation had not been attempted
Whether the FAA governs the arbitration provision (interstate commerce) Owner/Contractor argued the subcontract involved interstate commerce because it was a services contract between parties of different states Frohberg may have disputed applicability of FAA or its effect Court held the subcontract involved interstate commerce (Minnesota contractor, Nebraska subcontractor providing services) so the FAA applied, making the arbitration agreement presumptively enforceable
Remedy: whether stay and compel arbitration were required Owner/Contractor sought a stay and order compelling arbitration according to the general contract Frohberg sought to proceed in court Court reversed the district court and remanded with directions to stay the action and compel mediation, then arbitration if mediation fails

Key Cases Cited

  • Facilities Cost Mgmt. Group v. Otoe Cty. Sch. Dist., 291 Neb. 642 (Neb. 2015) (on contract interpretation and ambiguity)
  • David Fiala, Ltd. v. Harrison, 290 Neb. 418 (Neb. 2015) (state law governs formation questions of arbitration agreements)
  • Southland Corp. v. Keating, 465 U.S. 1 (U.S. 1984) (FAA requires state rules not to discriminate against arbitration)
  • Kindred Nursing Centers Ltd. v. Clark, 137 S. Ct. 1421 (U.S. 2017) (states must place arbitration agreements on equal footing with other contracts)
Read the full case

Case Details

Case Name: Frohberg Elec. Co. v. Grossenburg Implement
Court Name: Nebraska Supreme Court
Date Published: Jul 28, 2017
Citation: 297 Neb. 356
Docket Number: S-16-987
Court Abbreviation: Neb.