History
  • No items yet
midpage
Friends of the Santa Clara v. US Army Corps of Engineers
887 F.3d 906
9th Cir.
2018
Read the full case

Background

  • Newhall Land sought a Corps Section 404 permit to discharge dredged/fill material for the Newhall Ranch development in Los Angeles County; the project would affect ~12,000 acres including portions of the Santa Clara River and wetlands.
  • The Corps served as NEPA lead, prepared a combined EIS/EIR, issued a ROD and a provisional Section 404 permit in August 2011, and appended a Final Section 404(b)(1) Guidelines Evaluation selecting a modified on-site alternative (Modified Alternative 3) as the least environmentally damaging practicable alternative.
  • Environmental groups (SCOPE and Friends of the Santa Clara River, among others) sued alleging violations of the Clean Water Act (404(b)(1) practicable-alternatives requirement), NEPA (insufficient EIS/cumulative-impact analysis), and the ESA (failure to consult with NMFS, erroneous "no effect" finding for Southern California steelhead).
  • Key technical dispute centered on whether project discharges (notably dissolved copper concentrations) could affect downstream steelhead during storm events that connect flows past a normally dry reach (“Dry Gap”); Corps concluded modeled and background concentrations were below applicable benchmarks (California Toxics Rule) and would not affect steelhead.
  • District court granted summary judgment to Corps and Newhall Land; Ninth Circuit reviewed under the APA arbitrary-and-capricious standard, considered standing for NEPA and ESA claims, and addressed CWA, NEPA, and ESA challenges.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether Corps defined an impermissibly narrow "overall project purpose" for 404(b)(1) alternatives analysis Corps adopted applicant/Specific Plan objectives to narrow alternatives and preclude less-damaging sites Corps may and must consider applicant objectives and local land‑use decisions; it need not adopt a broader purpose Corps acted permissibly; considering applicant and county objectives was proper and not arbitrary
Whether Corps selected the least environmentally damaging practicable alternative and properly considered costs Corps should have required additional avoidance/minimization and used different cost metrics (per-unit, consider revenues, exclude land acquisition) Regulations permit cost consideration; Corps’ per‑acre and inclusion of land costs were reasonable and revenues need not be treated as "cost" Corps’ cost methodology and impracticability conclusion were reasonable and entitled to deference
Whether Corps violated ESA by determining Project "will have no effect" on steelhead and not consulting NMFS Project discharges may cause sublethal effects per NMFS technical memo; Corps failed to use best available science and should have consulted Corps relied on project-specific modeling, background data, and CTR benchmarks showing discharges below background/criteria; NMFS memo not directly applicable Corps’ no‑effect determination was not arbitrary or capricious; consultation not required
Whether Corps violated NEPA (inadequate cumulative‑impact analysis / failure to recirculate EIS after supplemental analysis) Final EIS/EIR failed to analyze cumulative dissolved‑copper impacts and Corps improperly relied on post‑EIS Supplemental Analysis without recirculation Final EIS/EIR adequately explained no‑effect conclusion; Supplemental Analysis merely confirmed findings and did not present significant new information NEPA requirements satisfied; no recirculation required; cumulative impacts discussion adequate

Key Cases Cited

  • United States v. Riverside Bayview Homes, 474 U.S. 121 (recognizing Corps authority over wetlands as "navigable waters")
  • Bering Strait Citizens for Responsible Res. Dev. v. U.S. Army Corps of Eng'rs, 524 F.3d 938 (9th Cir.) (standard for least environmentally damaging practicable alternative)
  • Jones v. Nat'l Marine Fisheries Serv., 741 F.3d 989 (9th Cir.) (Corps must determine overall project purpose and consider applicant objectives)
  • Sylvester v. U.S. Army Corps of Eng'rs, 882 F.2d 407 (9th Cir.) (applicant's project purpose may be accepted if genuine)
  • Nat'l Ass'n of Home Builders v. Defs. of Wildlife, 551 U.S. 644 (agency decisions reviewed for arbitrary and capricious standard)
  • Motor Vehicle Mfrs. Ass'n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29 (framework for arbitrary and capricious review)
  • Lujan v. Defs. of Wildlife, 504 U.S. 555 (Article III standing requirements explained)
Read the full case

Case Details

Case Name: Friends of the Santa Clara v. US Army Corps of Engineers
Court Name: Court of Appeals for the Ninth Circuit
Date Published: Apr 9, 2018
Citation: 887 F.3d 906
Docket Number: 15-56337
Court Abbreviation: 9th Cir.