History
  • No items yet
midpage
Franklin Mgt. Industries, Inc. v. Far More Properties, Inc.
25 N.E.3d 416
Ohio Ct. App.
2014
Read the full case

Background

  • FMI obtained a $1.1 million arbitration award against Motorcars and related entities in 2009.
  • The parties settled by a three-installment payment plan: $350,000 due no later than Jan 5, 2012; Jan 4, 2013; and Jan 4, 2014.
  • The settlement contract stated that if any payment was not received by 5:00 p.m. on the due date, FMI could file consent judgments and forego further actions; otherwise FMI would take no action on the judgments.
  • 2012 and 2013 payments were timely; for the 2014 payment, the bank delivered a certified check on Jan 3, 2014 but it was not delivered until Jan 6, 2014.
  • FMI sought to journalize a consent judgment under Exhibit D; Motorcars moved to compel FMI to file a satisfaction of judgment.
  • The trial court held there was reasonable compliance despite the missed deadline and denied journalization while granting the motion to compel satisfaction.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Was the 2014 deadline absolute for payment? FMI argues the late delivery by a third party should be excused and the payment fulfilled the obligation. Motorcars contends the deadline was absolute; a late payment breaches the agreement and triggers the consent judgments. Deadline is absolute; time was of the essence.
Did the trial court improperly apply equity to enforce contract terms? FMI contends the court should enforce the express terms without equity smoothing. Motorcars argues equitable considerations can justify non-strict enforcement. Court erred; express terms control and time is of the essence.
Did the court correctly resolve FMI's request to journalize the consent judgment and vacate the existing satisfaction order? FMI sought entry of Exhibit D consent judgment. Motorcars urged satisfaction of judgment be entered. Reversed and remanded to journalize the consent judgment; the satisfaction order vacated.

Key Cases Cited

  • Lake Ridge Academy v. Carney, 66 Ohio St.3d 376 (Ohio 1993) (time is of the essence when contract specifies dates and deadlines)
  • Master Builders, Inc. v. Hardcore Composites, 2006-Ohio-3729 (8th Dist. Cuyahoga) (upholds express terms when non-payment voids settlement)
  • Saunders v. Mortensen, 101 Ohio St.3d 86 (2004-Ohio-24) (contract construction is a matter of law)
  • Brown v. Brown, 90 Ohio App.3d 781 (11th Dist. 1993) (time of performance generally not of the essence unless specified)
Read the full case

Case Details

Case Name: Franklin Mgt. Industries, Inc. v. Far More Properties, Inc.
Court Name: Ohio Court of Appeals
Date Published: Dec 11, 2014
Citation: 25 N.E.3d 416
Docket Number: 101397
Court Abbreviation: Ohio Ct. App.