midpage
Sign in to see your projects.
329 P.3d 91
Wash. Ct. App.
2014
Read the full case

Background

  • Coluccio operated a 20-foot‑boom excavator in Broadway’s center turn lane beneath energized Metro trolley lines located ~12–15 feet above the road while replacing a sewer main. Inspector Paddock observed the boom within 10 feet of the lines on Feb. 11, 2011.
  • WAC 296‑155‑428(20)(a) requires a 10‑foot clearance from energized overhead lines; violation of that rule was cited as a serious WISHA violation.
  • Coluccio’s safety director and foreman knew the work would require operating within 10 feet of the lines but did not obtain a pre‑work variance; they relied on spotters and positioning instead.
  • At the time of inspection no limit switch, nylon sling, functioning strobe, painted clearance line, or dedicated spotter were in use; Paddock halted work and provided variance contact information.
  • Coluccio applied for a variance after the inspection proposing measures (training refreshers, daily prejob meetings, a dedicated safety watch, and installation of a limit switch); the Department granted an interim 4‑foot clearance with those safeguards for continued work.
  • The Department assessed a $1,200 penalty; the Board and superior court affirmed, finding Coluccio failed to prove an affirmative infeasibility defense.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether Coluccio established an affirmative infeasibility defense to the specific WAC 10‑ft requirement Coluccio: compliance was infeasible as the excavator never operated directly under the lines and it used planning, positioning, and electrical training to avoid contact Department: the regulation is presumed feasible; Coluccio failed to show impossibility or that no feasible alternatives existed and did not use feasible alternatives (spotter, limit switch) before inspection Held: Board’s rejection of infeasibility affirmed — substantial evidence supports finding Coluccio failed to prove infeasibility or use of feasible alternatives
Whether alternative safety measures proposed after inspection are relevant to the citation Coluccio: post‑inspection measures address future work and are irrelevant to the violation observed Department: alternatives (e.g., limit switch, dedicated spotter) were feasible and would have addressed the electrocution hazard the regulation targets Held: Court treated those alternatives as relevant evidence of feasible protections and noted Coluccio itself proposed a limit switch in its variance application
Whether the cited hazard was limited to ‘‘pulling the trench box’’ or encompassed general excavator operation within 10 ft Coluccio: citation concerned only trench‑box dragging beneath the lines Department/inspector: citation targeted operation of the excavator within 10 ft of energized lines, not just the box activity Held: Court agreed inspector cited general operation within 10 ft; employer cannot relabel the hazard to avoid the standard
Whether absence of an explicit regulation requiring limit switches prevents reliance on them as feasible alternatives Coluccio: no WAC mandates limit switches, so the Department cannot rely on their absence to defeat infeasibility Department: WAC need not list every feasible alternative; courts may consider practical, feasible measures Held: Court rejects Coluccio’s argument — feasibility of alternatives may be shown even if not specifically required by WAC; Coluccio’s failure to use multiple feasible measures was dispositive

Key Cases Cited

  • SuperValu, Inc. v. Dep’t of Labor & Indus., 158 Wn.2d 422 (2006) (burden and presumption that a specific standard is feasible; employer must prove infeasibility)
  • Wash. Cedar & Supply Co. v. Dep’t of Labor & Indus., 119 Wn. App. 906 (2004) (elements required to prove a serious WISHA violation)
  • Harry C. Crooker & Sons, Inc. v. Occupational Safety & Health Review Comm’n, 537 F.3d 79 (1st Cir. 2008) (framing infeasibility defense: compliance impossible or prevents work and alternatives undertaken or unavailable)
  • Spancrete Northeast, Inc. v. Occupational Safety & Health Review Comm’n, 905 F.2d 589 (2d Cir. 1990) (limits of relying on non‑specific general standards for prescribing particular protective equipment)
  • Asplundh Tree Expert Co. v. Dep’t of Labor & Indus., 145 Wn. App. 52 (2008) (Washington courts consult federal precedent interpreting analogous OSHA provisions)
Read the full case

Case Details

Case Name: Frank Coluccio Construction Co. v. Department of Labor & Industries
Court Name: Court of Appeals of Washington
Date Published: Mar 24, 2014
Citations: 329 P.3d 91; 181 Wash. App. 25; No. 70334-0-I
Docket Number: No. 70334-0-I
Court Abbreviation: Wash. Ct. App.
Log In