History
  • No items yet
midpage
Foulger-Pratt Residential Contracting, LLC v. Madrigal Condominiums, LLC
779 F. Supp. 2d 100
D.D.C.
2011
Read the full case

Background

  • Foulger-Pratt and Travelers seek judicial confirmation of an arbitration award against Madrigal in a DC District Court diversity case.
  • The project concerns Madrigal Lofts in Washington, D.C. with Glen Construction as original GC; Travelers issued performance/payment bonds.
  • The contract contemplated a three-member arbitration panel for disputes exceeding $100,000, with mediation attempted first.
  • Glen stopped paying subs in 2007; Foulger-Pratt took over the project, achieving substantial completion around June 2008.
  • An APS (partial settlement) in February 2009 designated a Project Neutral and reserved certain exterior-skin issues for arbitration, with a Gale Report basis.
  • Interim Award (Nov. 30, 2009) ordered due payments, an escrow for further payments, and reserved some attorney-fee determinations for a later interim award.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Governing law for arbitration review FAA governs review; preempts DC law. DC law applies per contract clause selecting DC law for arbitration. DC law applies; DCRAA governs review.
Vacatur grounds under DC law Vacatur grounds are narrow; challenge only specific portions. Panel exceeded authority or denied fair hearing on multiple items. DC review remains extremely limited; some vacatur grounds denied, others not proven.
Panel's jurisdiction over Exterior Skin claims Exterior Skin issues reserved for Project Neutral; Panel exceeded scope. Panel properly decided within its arbitration scope per APS and Gale carve-out. Panel had jurisdiction; Madrigal's challenge denied.
Pre-award interest on final payments Interest awards flow from Panel's merits findings and APS terms. Interest violates APS prerequisites to payment or contracts. No vacatur; Panel reasonably awarded pre-award interest.
Warranties/close-out and punch-list costs Panel could determine ongoing obligations and related warranties. Panel exceeded authority by altering close-out deliverables and warranties under APS. Claims denied; Panel acted within arbitration scope; no vacatur.

Key Cases Cited

  • Volt Information Sciences, Inc. v. Board of Trustees of the Leland Stanford Junior University, 489 U.S. 468 (1989) (FAA creates federal arbitrability law; choice of law governs arbitrability conflicts)
  • Mastrobuono v. Shearson Lehman Hutton, Inc., 514 U.S. 52 (1995) (general choice-of-law clauses vs. arbitration rules; context matters)
  • Jung v. Association of American Medical Colleges, 300 F. Supp. 2d 119 (D.D.C. 2004) (generic choice-of-law clause may not prove intent to opt out of FAA)
  • First Options of Chicago, Inc. v. Kaplan, 514 U.S. 938 (1995) (arbitrability questions generally decided by courts unless panel has jurisdiction)
  • Major League Baseball Players Ass'n v. Garvey, 532 U.S. 504 (2001) (extremely limited review of arbitration awards)
  • A1 Team USA Holdings, LLC v. Bingham McCutchen, LLP, 998 A.2d 320 (D.C. 2010) (DCRAA not expanding review beyond established limits)
Read the full case

Case Details

Case Name: Foulger-Pratt Residential Contracting, LLC v. Madrigal Condominiums, LLC
Court Name: District Court, District of Columbia
Date Published: Apr 27, 2011
Citation: 779 F. Supp. 2d 100
Docket Number: Case 1:09-cv-02333 (GK)
Court Abbreviation: D.D.C.