History
  • No items yet
midpage
Fleming v. Kent State Univ.
17 N.E.3d 620
Ohio Ct. App.
2014
Read the full case

Background

  • Fleming sued Kent State University for breach of a 28‑month employment contract to serve as Football Defensive Coordinator, with $71,500 annual salary, potential raises, bonuses (e.g., $6,000 for a bowl appearance), and a provided automobile; contract required NCAA compliance and reporting of outside income; an early termination cost provision applied if terminated pre‑June 30, 2012.
  • Hazell became head coach in Jan 2011; Kleinlein advised Fleming there would be no coaching job for him, signaling reassignment.
  • On Jan 21, 2011 Fleming was reassigned to a non‑coaching “assistant to the athletic director” position, effective Feb 14, 2011; Fleming did not accept.
  • Feb 18, 2011 letter stated Fleming must report for a 9:00 a.m. start on Feb 21, 2011 with continued pay and benefits but warned of discipline or termination for noncompliance; Fleming did not report.
  • March 7, 2011 President Lefton terminated Fleming for insubordination; Fleming received pay through March 15, 2011; KSU canceled vehicle deductions effective Feb 17, 2011.
  • Court of Claims found the contract silent on reassignment but held the reassignment breached the contract (constructive discharge analysis used by the trial court was deemed harmless error); the damages phase was limited to a court filing fee award, with the court ultimately sustaining the claim of breach and remanding on the damages issue regarding the liquidated damages clause.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Breach via reassignment to non‑coaching role Fleming argues reassignment breached the contract; the position change violated the agreed coaching role. KSU contends reassignment did not breach since contract did not expressly cover reassignment; reassignment not a coaching loss. Breach found; reassignment breached contract and constituted constructive discharge.
Constructive discharge applicability Working conditions became intolerable due to reassignment, forcing resignation. Reassignment alone did not render conditions intolerable; argument raised too late and not proven. Court held reassignment breached contract; constructive discharge analysis unnecessary for outcome.
Liquidated damages vs. penalty The liquidated damages clause should be enforced if damages were uncertain at contracting. Clause could be a penalty if damages were ascertainable and not uncertain. Court sustained the first prong’s finding that damages were uncertain; remand to assess remaining prongs and damages.

Key Cases Cited

  • Lake Ridge Academy v. Carney, 66 Ohio St.3d 376 (Ohio 1993) (test to distinguish liquidated damages from unenforceable penalties; reasonableness and relation to actual damages)
  • Samson Sales, Inc. v. Honeywell, Inc., 12 Ohio St.3d 27 (Ohio 1984) (liquidated damages framework; three-part test for enforceability)
  • Jones v. Stevens, 112 Ohio St. 43 (Ohio 1925) (authority on sentence for liquidated damages framework)
  • Mauzy v. Kelly Servs., Inc., 75 Ohio St.3d 578 (Ohio 1996) (constructive discharge and reasonable person standard)
  • O'Brien v. Ohio State Univ., 139 Ohio Misc.2d 36 (Ohio Misc. 2006) (damages under employment contracts with incentive components; uncertainty of future earnings)
Read the full case

Case Details

Case Name: Fleming v. Kent State Univ.
Court Name: Ohio Court of Appeals
Date Published: Aug 12, 2014
Citation: 17 N.E.3d 620
Docket Number: 13AP-942
Court Abbreviation: Ohio Ct. App.