History
  • No items yet
midpage
Fleck v. Missouri River Royalty Corp.
2015 ND 287
| N.D. | 2015
Read the full case

Background

  • Fleck (lessor) owns mineral rights and a 1972 oil and gas lease with a 10-year primary term and a habendum clause extending the lease "so long thereafter as oil or gas . . . is produced."
  • The Fleck 1 well produced after the primary term; production later declined and Fleck served notice of forfeiture in 2012 and sued to quiet title, alleging the lease terminated for failure to produce in paying quantities.
  • Defendants (lessees) counterclaimed, arguing the lease remained valid due to continued production and because operations to restore production were commenced within the lease’s 90-day savings clause period.
  • District court granted summary judgment for defendants, finding the lease extended by continued (albeit small) production and any cessations were temporary with timely restoration efforts.
  • The North Dakota Supreme Court held the district court misapplied the law: "production" in the habendum and savings clauses must mean "production in paying quantities," and whether paying-quantity production existed is a genuine issue of material fact requiring remand.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Does "production" in the habendum clause require production in paying quantities to extend the lease after the primary term? "Production" means production in paying quantities; lease terminated when Fleck 1 stopped producing profitably. "Production" can be any production; the well produced some oil and thus extended the lease. Held: "production" in the habendum clause means production in paying quantities.
Does the savings clause require commencement of operations within 90 days to restore paying-quantity production, or is any restoration effort enough even if not to paying quantities? Lessee must commence operations within 90 days to restore production to paying quantities (must begin work aimed at restoring paying-quantity production). Lessee’s commencement of operations and intermittent work sufficed even if paying-quantity production was not immediately restored. Held: The savings clause requires commencement of operations to restore production in paying quantities within 90 days (i.e., must begin efforts toward restoring paying-quantity production); lessee not required to restore paying quantities within 90 days but must commence appropriate operations.
Was summary judgment appropriate? The record (showing multi-year net losses) establishes no paying-quantity production after 2010, so summary judgment for Fleck is appropriate. Profit/loss snapshots are insufficient; factual inquiry (prudent operator standard, market, costs) makes summary judgment improper for defendants. Held: Summary judgment for defendants was improper; genuine issues of material fact exist about paying-quantity production and prudent-operator considerations; case remanded.

Key Cases Cited

  • Tank v. Citation Oil & Gas Corp., 848 N.W.2d 691 (N.D. 2014) (contracts and lease language construed to give effect to parties’ intent; discussed production/paying-quantity standard)
  • Johnson v. Shield, 868 N.W.2d 368 (N.D. 2015) (summary judgment standard on appeal)
  • Sorum v. Schwartz, 411 N.W.2d 652 (N.D. 1987) (production in paying quantities requires considering a reasonable time period and surrounding circumstances)
  • Clifton v. Koontz, 325 S.W.2d 684 (Tex. 1959) (two-step test: profit over operating costs over reasonable period and whether a prudent operator would continue production)
  • Olson v. Schwartz, 345 N.W.2d 33 (N.D. 1984) (lessee’s obligation to act as a reasonable and prudent operator in developing and protecting property)
Read the full case

Case Details

Case Name: Fleck v. Missouri River Royalty Corp.
Court Name: North Dakota Supreme Court
Date Published: Dec 7, 2015
Citation: 2015 ND 287
Docket Number: No. 20150106
Court Abbreviation: N.D.