History
  • No items yet
midpage
Fidelity & Deposit Co. v. Bondwriter Southwest, Inc.
228 Ariz. 84
| Ariz. Ct. App. | 2011
Read the full case

Background

  • Fidelity sued Bondwriter for breach of contract and negligence after Bondwriter issued incorrect bonds for the Flagstaff Project.
  • Agency agreement limited Bondwriter's authority to act only as expressly authorized, with Bondwriter liable for unauthorized acts by its agents.
  • Power of attorney instructed that Fidelity bonds must be submitted for approval before execution; Sparks and Stanton held power of attorney.
  • Bondwriter mistakenly issued $2,379,724 Flagstaff Project bonds instead of the approved ASU Project bonds; error discovered after delivery to Adaptive.
  • Copies of bonds were made and delivered to Flagstaff, which accepted them; Fidelity later paid claims totaling $875,735 and recovered some payments.
  • Trial court found Bondwriter breached the agency and power of attorney agreements and awarded Fidelity damages but allocated 5% fault to Bondwriter for contract damages, with others at fault for negligence; court awarded attorneys’ fees to Fidelity.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether comparative fault applies to contract damages Fidelity: fault allocation cannot reduce contract damages Bondwriter: UCATA fault apportionment applies to all damages Comparative fault does not apply to breach of contract damages; vacate and remand for revised judgment
Whether Fidelity ratified Bondwriter's actions Fidelity did not ratify; actions were to protect interests Bondwriter: ratification occurred by Fidelity’s affirmation of bonds Fidelity did not ratify Bondwriter's actions; ratification not shown
Whether Bondwriter breached the agency and power of attorney agreements Bondwriter prepared, signed, and delivered bonds without authorization, breaching agreements Bondwriter contends no breach unless execution occurred with Fidelity's authorization Bondwriter breached both the agency and power of attorney agreements by preparing, signing, and delivering unauthorized bonds
Whether Fidelity's contract damages were foreseeable and recoverable, and whether mitigation was properly applied Damages stemming from unauthorized bonds were foreseeable; Fidelity acted reasonably to mitigate Damages not foreseeable or should have been avoided by Fidelity Damages were foreseeable; Fidelity acted reasonably to mitigate; damages awarded on contract claim reinstated after remand

Key Cases Cited

  • Larson v. National Surety Co., 171 Minn. 455 (Minn. 1927) (treats delivery/issuance issues; relevant to execution and authorization)
  • All Am. Sch. Supply Co. v. Slavens, 125 Ariz. 231 (Ariz. 1980) (contract damages and foreseeability considerations)
  • Jimenez v. Sears, Roebuck and Co., 183 Ariz. 399 (Ariz. 1995) (UCATA and comparative fault framework in Arizona)
  • Haysville U.S.D. No. 261 v. GAF Corp., 233 Kan. 635 (Kan. 1983) (comparative negligence not proper in breach of contract actions)
  • Klingler Farms, Inc. v. Effingham Equity, Inc., 171 Ill.App.3d 567 (Ill. App. 1988) (refuses extension of comparative fault to contract actions)
  • Lesmeister v. Dilly, 330 N.W.2d 95 (Minn. 1983) (contract law typically not framed in fault terms)
  • Bd. of Educ. of the Hudson City Sch. Dist. v. Sargent, Webster, Crenshaw & Folley, 71 N.Y.2d 21 (N.Y. 1987) (contract damages not reduced by comparative negligence)
  • Sassen v. Tanglegrove Townhouse Condo. Ass'n, 877 S.W.2d 489 (Tex.App. 1994) (rejects applying comparative negligence to contract claims)
Read the full case

Case Details

Case Name: Fidelity & Deposit Co. v. Bondwriter Southwest, Inc.
Court Name: Court of Appeals of Arizona
Date Published: Jul 28, 2011
Citation: 228 Ariz. 84
Docket Number: 1 CA-CV 09-0612
Court Abbreviation: Ariz. Ct. App.