Farah, LLC v. Architura Corp.
952 N.E.2d 328
Ind. Ct. App.
2011
Read the full case

Background

  • Farah, LLC and Barrington Jewels, Inc. contracted with Architura to design, bid, and oversee renovations for a Barrington Jewels location at a former O’Charley’s in Indianapolis, for $40,000 plus $1,500 in expenses.
  • The contract allowed additional charges only for specified items, with major changes to design after schematic approval potentially triggering added fees.
  • During construction, bids exceeded Farah’s budget; Capitol Construction offered a bid around $747,000, with changes that later required added back items and costs, including $8,000 for steps Architura paid $5,000 of.
  • Architura filed a mechanic’s lien in August 2003; Farah paid $34,000 to release it; Architura filed a second lien in December 2003 for services beyond the original contract.
  • Farah deposited $50,300 with the trial court in September 2004 to release the second lien; Architura later sought additional fees and prejudgment interest.
  • A certificate of substantial completion was issued in November 2003; Architura and Capitol were involved in inspections, but Architura initially certified completion without inspecting, later being clarified by inspections before final funds release.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Mechanic’s lien amount limits Architura’s lien capped at contract balance, not the full value of services. Architura seeks reasonable value of its services beyond the contract price. Lien limited to contract balance; $7,500 remains, not $26,166.
Attorney fees under the mechanic’s lien Architura should recover fees under the lien. Fees justified by lien recovery should be awarded. Reverse award of $15,000 in fees; remand to set fees to $7,500 and recalculate prejudgment interest.
Failure to inspect and resulting damages Architura’s failure to inspect caused damages to Farah. Architects are not insurers; contract allowed limited inspections; no damages proven. No damages awarded for failure to inspect; breach not shown to cause damages.
Amount of damages for Architura’s breaches Costs for roof, insulation, lighting, and other items total over $206,081.55; should be awarded accordingly. Many costs are allocable to Capitol or exceed reasonableness; evidence supports a smaller award. Damages of $64,310 affirmed as within the record; full amount not awarded due to offsets and shared responsibility.

Key Cases Cited

  • Saint Joseph’s College v. Morrison, Inc., 302 N.E.2d 865 (Ind. Ct. App. 1973) (mechanic’s lien generally limited by amounts owed under contract)
  • Korellis Roofing, Inc. v. Stolman, 645 N.E.2d 29 (Ind. Ct. App. 1995) (lien amount tied to contract price)
  • Peter & Burghard Stone Co. v. Marion Nat. Bank of Marion, 153 N.E.2d 472 (Ind. 1926) (lien recovery not exceed contract amounts)
  • Walker v. Statzer, 284 N.E.2d 127 (Ind. Ct. App. 1972) (lien amount measured by agreed price between owner and contractor)
  • Clark’s Pork Farms v. Sand Livestock Systems, Inc., 563 N.E.2d 1292 (Ind. Ct. App. 1990) (mechanic’s lien fees forfeited if lien judgment not in sum)
  • Complete Elec. Co. v. Liberty Nat’l Bank and Trust Co., 530 N.E.2d 1216 (Ind. Ct. App. 1988) (mechanic’s lien fees denied when lien judgment defeated)
  • Nelson v. Marchand, 691 N.E.2d 1264 (Ind. Ct. App. 1998) (mechanic’s lien fees limited when owner prevails)
  • Mayberry Cafe, Inc. v. Glenmark Constr. Co., Inc., 879 N.E.2d 1162 (Ind. Ct. App. 2008) (architect not insurer of contractor’s work absent special agreement)
Read the full case

Case Details

Case Name: Farah, LLC v. Architura Corp.
Court Name: Indiana Court of Appeals
Date Published: Aug 12, 2011
Citation: 952 N.E.2d 328
Docket Number: No. 49A05-1012-PL-793
Court Abbreviation: Ind. Ct. App.