Exelis, Inc.
ASBCA No. 58966
| A.S.B.C.A. | Mar 29, 2017Background
- Exelis (intermediate home office formerly part of ITT) paid long-term incentive plan (LTIP) TSR awards in cash to executives based on a relative total shareholder return (TSR) metric comparing Exelis stock price changes and dividends to peers over a three-year period. 2004–2006 TSR payout occurred in January 2007.
- Exelis included TSR awards and a $7,050 holiday-band entertainment cost in its FY 2006 indirect cost proposal, which it certified as a final indirect cost proposal under FAR 52.216-7(d)(2)(i).
- DCAA/DCMA audits (2006–2012) reviewed FY 2004–2006 submissions; DCAA/DCMA concluded the TSR awards were calculated from securities price changes and dividends and thus unallowable under FAR 31.205-6(i); entertainment costs were unallowable under FAR 31.205-14.
- DCMA CACO assessed a penalty under FAR 42.709 (implementing 10 U.S.C./41 U.S.C. penalty provisions) for including expressly unallowable costs in a final indirect cost proposal; Exelis appealed to the ASBCA.
- Exelis argued TSR awards were not covered by FAR 31.205-6(i) because they were paid from a predetermined award pool (an incentive, not stock-based/deferred compensation), pointed to prior government audit silence/communications and other contractors’ differing treatments, and sought waiver of the entertainment penalty under FAR 42.709-5(c).
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Are Exelis's TSR cash awards allowable under FAR 31.205-6(i)? | TSR is an incentive based on a preset award pool and thus not compensation "based on changes in prices of corporate securities"; therefore allowable. | TSR payouts are calculated/valued from stock-price changes and dividends (TSR metric) and fall within FAR 31.205-6(i). | Held: Unallowable. TSR awards are calculated/valued based on securities price changes and dividend payments and are expressly unallowable under FAR 31.205-6(i). |
| Is the contracting officer’s penalty for including expressly unallowable costs in a final indirect cost proposal proper? | Penalty improper because government positions changed and audits earlier did not reject TSR; also submission was not a final indirect cost rate proposal. | Exelis certified the submission as a final indirect cost proposal under FAR 52.216-7; the costs were expressly unallowable, so penalty authorized under FAR 42.709/ statute. | Held: Penalty proper. The 2006 submission was a final indirect cost proposal and penalties were correctly imposed for expressly unallowable costs. |
| Was waiver of the entertainment-cost penalty required under FAR 42.709-5(b) ($10,000 threshold)? | Entertainment cost was only $7,050, below $10,000, so waiver required. | Waiver threshold applies to total expressly unallowable costs in the submission, not a single category; total exceeded $10,000. | Held: No waiver. Total expressly unallowable costs (TSR + entertainment) exceeded $10,000. |
| Was waiver of the entertainment-cost penalty required under FAR 42.709-5(c) (inadvertent inclusion + internal controls)? | Exelis had policies/training/controls (later-dated materials) demonstrating inadvertence and controls to preclude such inclusions. | Exelis failed to provide contemporaneous evidence to the contracting officer showing controls in place at the time; submitted documents post‑dating the proposal and inadequate pre‑existing documents. | Held: No waiver. Exelis did not satisfy FAR 42.709-5(c) because it did not provide evidence to the contracting officer that effective policies/controls existed when the proposal was submitted. |
Key Cases Cited
- M Eagles Tool Warehouse, Inc. v. Fisher Tooling Co., 439 F.3d 1335 (Fed. Cir. 2006) (use of "such as" in regulation indicates examples are non‑exhaustive)
- Ratzlaf v. United States, 510 U.S. 135 (U.S. 1994) (courts rely on plain text of an unambiguous regulation rather than regulatory history)
- Frederick v. Shinseki, 684 F.3d 1263 (Fed. Cir. 2012) (same principle regarding reliance on plain regulatory language)
