Everette Hamner, Jennifer Hamner, Judy Skogman, and Susan Himes v. City of Bettendorf, Iowa, an Iowa Municipal Corporation
15-2154
Iowa Ct. App.Oct 12, 2016Background
- Landowners (Hamner, Skogman, Himes) own lots in Rolling Meadows adjacent to Stafford Creek; each lot is subject to 25-foot-wide utility/drainage easements granted in 1968.
- Dedication and 1968 easement language authorized installation, maintenance, and renewal of utilities and storm/sanitary drainage within the mapped easement areas.
- Bettendorf adopted a Stafford Creek Stream Bank Improvement Project that would remove trees, regrade the 25-foot easement area, install retaining walls, rock rip-rap, fencing, and other permanent alterations to stabilize the creek.
- City sought appointment of a compensation commission for a 7.5-foot temporary construction easement north of the 25-foot easement; City refused to pay compensation for permanent changes within the 25-foot easement, claiming easement rights allowed the work.
- Landowners sought injunction and argued the Project exceeded the easement scope and constituted a taking requiring compensation; district court granted summary judgment for landowners, ruling the Project exceeded the easement and required condemnation/just compensation.
- City appealed; the Court of Appeals affirmed, holding the proposed work placed a greater burden than contemplated by the 1968 easements and therefore required compensation under the Iowa Constitution.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether the City’s proposed streambank-stabilization work falls within the scope of the 1968 utility/drainage easements | Easements permit only maintenance and installation of utilities and drainage infrastructure; the City’s large-scale regrading, tree removal, walls, rip-rap, and fencing exceed that scope and thus require condemnation/compensation | The easements were granted for storm sewer/drainage and utility purposes across the mapped 25-foot area; the City may alter topography and perform stabilization without additional compensation | Held for plaintiffs: the Project materially exceeds the easement’s contemplated uses and imposes greater burden, so it constitutes a taking requiring compensation and condemnation proceedings |
| Whether summary judgment was appropriate given undisputed facts and solely legal issues | Facts undisputed; legal determination on easement scope suitable for summary judgment | Same | Held: summary judgment proper to decide scope and taking as a matter of law |
Key Cases Cited
- Stew-Mc Dev., Inc. v. Fisher, 770 N.W.2d 839 (Iowa 2009) (scope of an easement is limited to uses contemplated at formation; uncontemplated expanded use may require compensation)
- Keokuk Junction Ry. Co. v. IES Indus., Inc., 618 N.W.2d 352 (Iowa 2000) (sets three-factor test to determine easement scope: past physical use, easement purpose, and additional burden on servient estate)
- Kucera v. Baldazo, 745 N.W.2d 481 (Iowa 2008) (standard of review for equitable summary judgment)
- Hawk v. Rice, 325 N.W.2d 97 (Iowa 1982) (definitions and nature of easements)
- Gray v. Osborn, 739 N.W.2d 855 (Iowa 2007) (easement principles regarding dominant and servient estates)
- Schwob v. Green, 215 N.W.2d 240 (Iowa 1974) (easement use limited to parties’ intent)
- Flynn v. Mich.–Wis. Pipeline Co., 161 N.W.2d 56 (Iowa 1968) (what is reasonably necessary for the easement’s particular purpose is considered)
