History
  • No items yet
midpage
892 F.3d 321
D.C. Cir.
2018
Read the full case

Background

  • West Deptford submitted a PJM interconnection request in 2006; PJM studies assigned West Deptford potential liability for a $13 million network upgrade (Network Upgrade 28) under the then-active PJM Tariff § 37.7.
  • While West Deptford’s request was pending, PJM filed tariff amendments (2008 Tariff) including § 219, which changed the rule for assigning cost responsibility for prior upgrades; PJM requested an August 1, 2008 effective date for the revisions.
  • PJM and the Commission disagreed about whether the new § 219 applied to interconnection agreements filed after the effective date or only to projects entering the queue after that date; PJM’s transmittal and answers were ambiguous on prospectivity.
  • PJM ultimately sought to impose the pre‑2008 cost allocation on West Deptford; FERC initially ruled the old § 37.7 governed because West Deptford entered the queue before the amendment, and denied rehearing.
  • This court vacated and remanded, finding FERC had not adequately explained how its decision aligned with statute, precedent, and the filed-rate doctrine; on remand FERC reversed, applying § 219 and interpreting its five‑year window to run from execution of the interconnection agreement.
  • Marcus Hook petitioned for review of the remand decision, arguing FERC’s selection of § 219 and its interpretation (execution date as the relevant trigger) were arbitrary, conflicted with precedent and evidence, and undermined the filed-rate doctrine.

Issues

Issue Plaintiff's Argument (Marcus Hook) Defendant's Argument (FERC/PJM) Held
Which tariff governs cost allocation for an interconnection agreement executed after a tariff amendment but entered in the queue before the amendment? Old § 37.7 governs because West Deptford entered the queue before the amendment and had notice of costs. New § 219 governs for interconnection agreements filed/executed after the amendment’s effective date absent explicit grandfathering. FERC’s determination that § 219 governs was reasonable and upheld.
What is the operative date for § 219’s five‑year look‑back period? The look‑back should be queue entry or the study date when upgrade necessity was identified. The five‑year period reasonably runs from execution of the interconnection service agreement. Court defers to FERC and upholds execution‑date interpretation as reasonable.
Did FERC adequately justify changing its prior position on remand? FERC failed to address extrinsic evidence and prior practice; change was arbitrary. FERC relied on this Court’s prior finding that PJM’s transmittal and answers were ambiguous and explained reasons on remand. FERC provided a reasoned explanation; the change was lawful and not arbitrary.
Did FERC ignore relevant evidence or arguments on remand (e.g., related proceedings or facilities studies)? Evidence in related proceedings and facilities studies show § 219 should not apply to West Deptford. Court’s prior opinion rejected those materials as dispositive; facilities studies are non‑binding estimates; objections were addressed or waived. Court finds FERC permissibly relied on the record and this Court’s earlier analysis; claims of ignored evidence are rejected.

Key Cases Cited

  • W. Deptford Energy, LLC v. FERC, 766 F.3d 10 (D.C. Cir. 2014) (prior opinion finding FERC’s initial reasoning inadequate and remanding)
  • FPL Energy Marcus Hook, L.P. v. FERC, 430 F.3d 441 (D.C. Cir. 2005) (prior Court decision upholding FERC on related network upgrade cost allocation dispute)
  • Maislin Indus., U.S., Inc. v. Primary Steel, Inc., 497 U.S. 116 (1990) (filed‑rate doctrine and requirement that utilities file rates openly)
  • Old Dominion Elec. Co‑Op., Inc. v. FERC, 518 F.3d 43 (D.C. Cir. 2008) (deference standard for Commission interpretation of tariffs)
Read the full case

Case Details

Case Name: Esi Energy, LLC v. Fed. Energy Regulatory Comm'n
Court Name: Court of Appeals for the D.C. Circuit
Date Published: Jun 8, 2018
Citations: 892 F.3d 321; 16-1342
Docket Number: 16-1342
Court Abbreviation: D.C. Cir.
Log In
    Esi Energy, LLC v. Fed. Energy Regulatory Comm'n, 892 F.3d 321