History
  • No items yet
midpage
EQT Production Co. v. Department of Environmental Protection
130 A.3d 752
| Pa. | 2015
Read the full case

Background

  • EPC (EQT Production Co.) discovered contaminated water leaking from a subsurface impoundment in May 2012, cleaned the site, and began remediation under Pennsylvania’s Act 2.
  • DEP asserted violations of the Clean Streams Law and proposed a consent assessment seeking about $1.27 million in May 2014, including large sums for alleged continuing daily violations; later DEP filed a civil-penalty complaint seeking over $4.5 million plus daily penalties before the Environmental Hearing Board (EHB).
  • EPC filed an original-jurisdiction declaratory judgment action in the Commonwealth Court challenging DEP’s “continuing-violation” interpretation (i.e., that mere continued presence of contaminants generates daily penalties) and argued administrative remedies were inadequate or unavailable.
  • DEP objected, asserting exclusive EHB jurisdiction, exhaustion requirements, and that any alleged harm was speculative until the EHB imposed penalties.
  • The Commonwealth Court sustained DEP’s preliminary objections; the Pennsylvania Supreme Court reversed, holding EPC’s pre-enforcement challenge presented an actual controversy warranting declaratory relief and that exhaustion of administrative remedies was unnecessary under these facts.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Availability of pre-enforcement declaratory relief to challenge DEP’s statutory interpretation EPC: DEP’s continuing-violation interpretation imposes immediate, substantial, multi‑million‑dollar exposure — courts should decide legal questions now DEP: EHB has exclusive jurisdiction; declaratory relief is barred while administrative remedies are available; harm is speculative Court: Allowed pre-enforcement declaratory review — actual controversy existed and administrative exhaustion unnecessary here
Nature of the legal question (pure law vs. factual) EPC: Dispute is primarily a question of statutory interpretation, not factfinding DEP: Application involves factual development and EHB expertise; review belongs to EHB first Court: Found the dispute predominantly a legal question suitable for judicial review
Effect of agency’s nonbinding position and timing of EHB filing EPC: DEP’s threat of accumulating penalties and inability to obtain relief administratively before DEP filed makes judicial review necessary DEP: DEP cannot impose penalties without EHB; until EHB acts harm is speculative; EHB later filed its own complaint Court: Timing did not defeat EPC’s jurisdiction; DEP’s later EHB filing did not cure the hardship or render EPC’s suit premature
Scope of precedent limiting pre-enforcement review (Donahue/Arsenal Coal) EPC: Donahue and Arsenal Coal support pre-enforcement review where administrative positions inflict direct, immediate burdens DEP: Those cases do not apply because DEP cannot itself impose penalties and EHB has exclusive adjudicatory role Court: Applied Donahue/Arsenal Coal line — formality of agency action is not dispositive where burdens are direct and immediate

Key Cases Cited

  • Donahue v. Office of Open Records, 626 Pa. 437, 98 A.3d 1223 (Pa. 2014) (framework for declaratory relief, actual controversy, and pre‑enforcement review)
  • Arsenal Coal Co. v. Commonwealth, 505 Pa. 198, 477 A.2d 1333 (Pa. 1984) (pre‑enforcement challenges allowed when regulations have direct and immediate burdens)
  • Bayada Nurses, Inc. v. DLI, 607 Pa. 527, 8 A.3d 866 (Pa. 2010) (pre‑enforcement review justified to avoid substantial operational burdens and piecemeal enforcement)
  • Sackett v. EPA, 132 S. Ct. 1367 (U.S. 2012) (federal pre‑enforcement review principles and concerns about agency power to impose escalating penalties without timely judicial redress)
Read the full case

Case Details

Case Name: EQT Production Co. v. Department of Environmental Protection
Court Name: Supreme Court of Pennsylvania
Date Published: Dec 29, 2015
Citation: 130 A.3d 752
Court Abbreviation: Pa.