Entergy Nuclear Palisades, LLC v. United States
2016 U.S. Claims LEXIS 1487
Fed. Cl.2016Background
- Entergy Nuclear Palisades (Entergy) operates Palisades plant; DOE agreed under the Standard Contract to begin accepting spent nuclear fuel (SNF) by Jan. 31, 1998 but never did; Entergy (and predecessor) paid fees into the program.
- Entergy acquired Palisades in 2007; this suit seeks mitigation costs incurred April 11, 2007–June 30, 2013 after government breach; partial judgment already awarded $20.6M and government conceded an additional $3,504,856 post-trial.
- Major contested damage categories: (1) replacement of deteriorated Carborundum racks in the spent fuel pool (re-rack) and removal of stuck assemblies, (2) costs to load SNF into dry storage canisters and construct a second ISFSI (including delay-related standby costs), and (3) full-time security staffing for the second ISFSI.
- Entergy’s position: re-rack and related dry-storage work were undertaken but-for DOE’s failure to remove SNF; re-rack was a reasonable permanent mitigation compared to repeated temporary measures or more frequent dry-storage campaigns.
- Government’s position: many costs either would have been incurred regardless (racks were defective), were not sufficiently caused by the breach (liberation of stuck fuel), or were the result of Entergy’s own errors/unexplained delays (standby costs); it conceded certain dry-cask loading costs after System Fuels.
- Court outcome (damages): awarded Entergy $13,828,676 (including the post-trial concession). Court found re-rack recoverable (but not costs to liberate stuck assemblies), awarded certain dry-storage loading and track-alley structural review costs, denied delay/standby costs caused by Entergy’s errors, and awarded full security staffing for both posts.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether re-racking Region I was caused by DOE breach / but-for requirement | Re-rack was undertaken because DOE’s nonperformance left too much fuel in pool; in but-for world fewer assemblies would remain and re-rack would not be needed | Racks were defective and would have been replaced anyway; re-rack was unreasonable compared to adding dry storage | Re-rack was caused by breach and was a reasonable mitigation; recoverable (except costs to free stuck assemblies) |
| Recovery for liberating stuck fuel assemblies | Costs incurred to free assemblies were part of the re-rack project and claimed as mitigation | DOE: assemblies would have to be prepared/removed by Entergy even if DOE performed; costs not caused by breach | Not recoverable — DOE not but-for cause of liberation costs; Entergy would have had to remove them when DOE performed |
| Dry-cask loading and standby/delay costs | Loading costs were necessary mitigation; delay standby costs were part of campaign expenses | DOE conceded post-System Fuels liability for loading costs but disputes $945,331 in standby/wait costs as Entergy-caused or unexplained | Court awarded loading costs including conceded $3,504,856; denied delay/standby costs caused by Entergy’s errors or unexplained delays |
| Security staffing for second ISFSI | Two 24/7 posts were required by NRC and staffed; costs are incremental mitigation damages caused by DOE breach | DOE disputed proof that both posts were consistently staffed and that claimed labor was incremental | Court credited security manager testimony and found both posts staffed; awarded full security staffing costs (additional $629,603) |
Key Cases Cited
- System Fuels, Inc. v. United States, 818 F.3d 1302 (Fed. Cir. 2016) (government liable for on-site dry fuel loading costs under Standard Contract breach)
- Yankee Atomic Elec. Co. v. United States, 536 F.3d 1268 (Fed. Cir. 2008) (but-for causation and plaintiff burden to show non-breach financial condition for mitigation damages)
- Robinson v. United States, 305 F.3d 1330 (Fed. Cir. 2002) (no recovery for damages avoidable by reasonable efforts)
- Energy Nw. v. United States, 641 F.3d 1300 (Fed. Cir. 2011) (standard for proving internal mitigation costs and reasonable certainty)
- Sacramento Mun. Util. Dist. v. United States, 70 Fed. Cl. 332 (2006) (government bears burden to show mitigation efforts were unreasonable)
