History
  • No items yet
midpage
Entergy Nuclear Indian Point 2, LLC v. United States
128 Fed. Cl. 526
| Fed. Cl. | 2016
Read the full case

Background

  • Entergy Nuclear Indian Point 2 sued the United States for damages from DOE’s partial breach of the 1983 Standard Contract to begin accepting spent nuclear fuel by Jan. 31, 1998; trial covered mitigation costs from Aug. 31, 2008 to June 30, 2013.
  • Entergy sought $35,650,752; the government contested $7,847,288 of that amount. The court awarded a total of $34,469,598.
  • Key mitigation steps by Entergy: built and staffed dry storage (Part 72) at Indian Point 2, purchased and loaded canisters, performed fuel characterization and repairs, removed contaminated soil, and paid NRC fees and vendor charges.
  • Legal framework: damages for partial breach aim to put plaintiff in the position had the contract been performed; plaintiff must prove foreseeability, causation (but-for), and damages with reasonable certainty; defendant bears burden to show unreasonable mitigation.
  • The court applied Federal Circuit precedent (including System Fuels, Vermont Yankee, Energy Northwest, Consolidated Edison) to relax strict hypothetical non-breach modeling where government actions or future regulatory requirements are uncertain.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Recoverability of security staffing costs ($2,355,777) Staffing the two bullet-resistant enclosures was required by NRC and caused by DOE’s breach; hours can be reasonably estimated from staffing needs Records were destroyed; lack of shift-level proof and collateral estoppel from other Entergy cases Awarded: court found 24/7 staffing proven, costs reasonably calculated despite destroyed rosters; collateral estoppel inapplicable
North Anna-type fuel repair costs ($1,599,939) Repairs were avoidable in a non-breach world because many assemblies could have been shipped to DOE before industry notices and slippage Repairs would have been required even if DOE performed; inspections would have revealed cracking Awarded: court found sufficient evidence that many assemblies would have been shipped pre-2002/2007 and repairs were caused by the breach
Fuel characterization and debris removal ($625,823) Necessary to load Holtec storage casks; future re-characterization uncertainty attributable to Government; System Fuels supports recovery Government argues characterization may suffice for later transport and thus is not a breach-caused cost Awarded: court followed System Fuels and Consolidated Edison reasoning; characterization costs caused by breach and uncertainty favors plaintiff
Repairs to fuel handling machine and overhead crane ($134,529) Repairs were incurred during mitigation and thus recoverable Repairs were routine plant maintenance/wear-and-tear and would have been incurred in non-breach world Denied: court held plaintiff failed to prove these repairs wouldn’t have been required absent the breach
NRC Part 171 (generic) fees ($879,112) Increased Part 171 assessments (post-1999 rule change) were caused by DOE’s breach Rule change rationale did not reference DOE; precedent (Consolidated Edison II) holds fee change not caused by breach Denied: bound by Consolidated Edison II and related decisions; Part 171 fees not recoverable
Holtec expediting fees & interest ($167,513) Fees incurred due to expedited cask order caused by DOE’s breach Fees resulted from Entergy’s failure to order within contract lead time; unreasonable mitigation Denied: court found Entergy unreasonably delayed ordering and should bear the cost

Key Cases Cited

  • Indiana Michigan Power Co. v. United States, 422 F.3d 1369 (Fed. Cir.) (sets foreseeability, causation, reasonable-certainty framework for NWPA breach damages)
  • System Fuels, Inc. v. United States, 818 F.3d 1307 (Fed. Cir.) (allows recovery where government leaves future performance/regulation uncertain; relaxes strict non-breach modeling)
  • Vermont Yankee Nuclear Power Corp. v. United States, 683 F.3d 1330 (Fed. Cir.) (requires comparison to a hypothetical non-breach world unless uncertainty prevents meaningful modeling)
  • Energy Northwest v. United States, 641 F.3d 1300 (Fed. Cir.) (discusses plaintiff’s burden to model non-breach world; addresses effect of government hindrance)
  • Consolidated Edison Co. of N.Y. v. United States, 676 F.3d 1331 (Fed. Cir.) (addresses NRC fee rule change and recoverability of Part 171 fees)
  • Pacific Gas & Electric Co. v. United States, 536 F.3d 1282 (Fed. Cir.) (interprets ACR/MPA acceptance process under the Standard Contract)
  • Yankee Atomic Electric Co. v. United States, 536 F.3d 1268 (Fed. Cir.) (but-for causation and damages principles in spent fuel cases)
  • San Carlos Irrigation & Drainage Dist. v. United States, 111 F.3d 1557 (Fed. Cir.) (standards for certainty of damages)
  • Boston Edison Co. v. United States, 658 F.3d 1361 (Fed. Cir.) (addressed wet storage costs but did not decide Part 171 causation issue)
Read the full case

Case Details

Case Name: Entergy Nuclear Indian Point 2, LLC v. United States
Court Name: United States Court of Federal Claims
Date Published: Oct 5, 2016
Citation: 128 Fed. Cl. 526
Docket Number: 13-619C
Court Abbreviation: Fed. Cl.