midpage
Projects
Sign in to see your projects.
109 F.4th 583
D.C. Cir.
2024
Read the full case

Background

  • In response to a 2021 cold snap that exposed growing grid reliability issues, the Midcontinent Independent System Operator (MISO) proposed significant revisions to its capacity market, shifting to a seasonal market, changing resource accreditation methodologies, and updating planned outage rules.
  • The Federal Energy Regulatory Commission (FERC) approved these changes after finding them just and reasonable, and denied rehearing requests from various stakeholders.
  • Entergy, a group of utilities operating in several southern states and members of MISO, challenged three specific aspects: the new capacity accreditation methodology, a rule requiring replacement capacity for outages over 31 days/season, and a 120-day advance notice requirement for planned outages.
  • The D.C. Circuit reviewed the case under the arbitrary-and-capricious standard of the Administrative Procedure Act, focusing only on issues properly preserved by Entergy.
  • Intervenors supported Entergy on the overlapping issues but also raised additional arguments, most of which were not addressed due to jurisdictional or procedural limitations.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Capacity Accreditation Weighting Overweights a small subset of hours, causing volatility New method is more accurate for peak demand periods FERC’s approval upheld
Volatility in Accreditation Volatility imposes costs and planning uncertainty System-wide and participant-level volatility is low FERC’s approval upheld
31-Day Outage Replacement Rule Unduly burdens units needing longer maintenance Rule balances reliability and maintenance needs FERC’s approval upheld
120-Day Notice for Planned Outages Not adequately justified; shorter notice possible Needed for planning and reliability coordination FERC’s approval upheld

Key Cases Cited

  • Public Citizen v. FERC, 7 F.4th 1177 (D.C. Cir. 2021) (describing how MISO’s capacity market operates)
  • Ameren Servs. Co. v. FERC, 893 F.3d 786 (D.C. Cir. 2018) (discussing the Federal Power Act's exhaustion requirement)
  • New England Power Generators Ass’n v. FERC, 879 F.3d 1192 (D.C. Cir. 2018) (addressing the jurisdictional nature of the exhaustion requirement)
  • Petal Gas Storage, LLC v. FERC, 496 F.3d 695 (D.C. Cir. 2007) (FERC need only choose a reasonable solution, not the best one)
  • California Dep’t of Water Res. v. FERC, 306 F.3d 1121 (D.C. Cir. 2002) (intervenors generally limited to issues raised by petitioners)
Read the full case

Case Details

Case Name: Entergy Arkansas, LLC v. FERC
Court Name: Court of Appeals for the D.C. Circuit
Date Published: Jul 26, 2024
Citations: 109 F.4th 583; 22-1335
Docket Number: 22-1335
Court Abbreviation: D.C. Cir.
Log In