Energy Harbor, LLC v. FERC
24-1092
| D.C. Cir. | Jul 11, 2025Background
- PJM Interconnection, L.L.C. operates the largest competitive wholesale energy market in the U.S. and has an FERC-approved Tariff that penalizes electricity generators for underperformance during emergency periods.
- Energy Harbor, LLC owns the W.H. Sammis Plant and was penalized over $12 million for failing to meet its capacity commitments during a severe winter storm in December 2022.
- The penalties were based on PJM’s Tariff, which included a pay-for-performance model and a potential exception for shortfalls solely caused by planned or maintenance outages approved by PJM.
- Energy Harbor filed a complaint with FERC, challenging PJM’s calculation and application of penalties, arguing for a broader interpretation of the outage exception.
- FERC found PJM’s penalty calculations and construction of the Tariff appropriate and denied rehearing; Energy Harbor petitioned the D.C. Circuit for review.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Interpretation of Tariff’s maintenance outage exception (Section 10A(d)) | Exception applies whenever capacity is unavailable due to approved maintenance, reducing penalties regardless of other causes | Exception only applies when maintenance outage solely causes the shortfall; forced outages count against exemption | Court sided with FERC: Outage must be sole cause of nonperformance. |
| Basis for shortfall calculation | Calculation should use only Resource Committed Capacity (adjusted for past outages), not total Installed Capacity | Tariff requires assessment of entire Installed Capacity, not just commitments | Court agreed with FERC: Installed Capacity underpins performance computation. |
| Unit-by-unit assessment for outages | Excusal should be assessed per generator unit, crediting maintenance at unit level | Excusal applies at facility (plant) level, not at individual units | Court adopted FERC’s view: exemption applies at plant level. |
| Adequacy of FERC’s rehearing process | Failure to issue a substantive order denying rehearing was arbitrary and capricious | FERC can decline by operation of law under statute and precedent | Court held FERC’s process was proper under governing law. |
Key Cases Cited
- Advanced Energy Mgmt. Alliance v. FERC, 860 F.3d 656 (D.C. Cir. 2017) (upholding FERC approval of PJM's pay-for-performance penalty structure)
- Keyspan-Ravenswood, LLC v. FERC, 474 F.3d 804 (D.C. Cir. 2007) (discussing calculation of installed and unforced capacity in PJM markets)
- Allegheny Def. Project v. FERC, 964 F.3d 1 (D.C. Cir. 2020) (en banc) (affirming FERC's ability to issue rehearing denials by operation of law)
