History
  • No items yet
midpage
Energy Harbor, LLC v. FERC
24-1092
| D.C. Cir. | Jul 11, 2025
Read the full case

Background

  • PJM Interconnection, L.L.C. operates the largest competitive wholesale energy market in the U.S. and has an FERC-approved Tariff that penalizes electricity generators for underperformance during emergency periods.
  • Energy Harbor, LLC owns the W.H. Sammis Plant and was penalized over $12 million for failing to meet its capacity commitments during a severe winter storm in December 2022.
  • The penalties were based on PJM’s Tariff, which included a pay-for-performance model and a potential exception for shortfalls solely caused by planned or maintenance outages approved by PJM.
  • Energy Harbor filed a complaint with FERC, challenging PJM’s calculation and application of penalties, arguing for a broader interpretation of the outage exception.
  • FERC found PJM’s penalty calculations and construction of the Tariff appropriate and denied rehearing; Energy Harbor petitioned the D.C. Circuit for review.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Interpretation of Tariff’s maintenance outage exception (Section 10A(d)) Exception applies whenever capacity is unavailable due to approved maintenance, reducing penalties regardless of other causes Exception only applies when maintenance outage solely causes the shortfall; forced outages count against exemption Court sided with FERC: Outage must be sole cause of nonperformance.
Basis for shortfall calculation Calculation should use only Resource Committed Capacity (adjusted for past outages), not total Installed Capacity Tariff requires assessment of entire Installed Capacity, not just commitments Court agreed with FERC: Installed Capacity underpins performance computation.
Unit-by-unit assessment for outages Excusal should be assessed per generator unit, crediting maintenance at unit level Excusal applies at facility (plant) level, not at individual units Court adopted FERC’s view: exemption applies at plant level.
Adequacy of FERC’s rehearing process Failure to issue a substantive order denying rehearing was arbitrary and capricious FERC can decline by operation of law under statute and precedent Court held FERC’s process was proper under governing law.

Key Cases Cited

  • Advanced Energy Mgmt. Alliance v. FERC, 860 F.3d 656 (D.C. Cir. 2017) (upholding FERC approval of PJM's pay-for-performance penalty structure)
  • Keyspan-Ravenswood, LLC v. FERC, 474 F.3d 804 (D.C. Cir. 2007) (discussing calculation of installed and unforced capacity in PJM markets)
  • Allegheny Def. Project v. FERC, 964 F.3d 1 (D.C. Cir. 2020) (en banc) (affirming FERC's ability to issue rehearing denials by operation of law)
Read the full case

Case Details

Case Name: Energy Harbor, LLC v. FERC
Court Name: Court of Appeals for the D.C. Circuit
Date Published: Jul 11, 2025
Docket Number: 24-1092
Court Abbreviation: D.C. Cir.