History
  • No items yet
midpage
Enbridge Energy Limited Partnership v. Upper Peninsula Power Co
313 Mich. App. 669
| Mich. Ct. App. | 2015
Read the full case

Background

  • UPPC filed for a >$12 million electric rate increase in 2009; parties (including PSC Staff) signed a settlement that implemented a revenue decoupling mechanism (RDM) for UPPC for test year 2010 and the PSC approved it.
  • Enbridge, not a party to the original rate case, later challenged the PSC’s authority to approve the RDM and filed a formal complaint after the PSC denied its rehearing petition for lack of standing.
  • This Court decided Detroit Edison while UPPC’s RDM reconciliation was pending, holding MCL 460.1097(4) authorizes only study/reporting for electric RDMs and does not authorize implementation (contrasting the explicit gas-utility RDM authorization in MCL 460.1089(6)).
  • The PSC defended approval of the settlement-RDM by relying on its general rate-setting authority and Dodge v Detroit Trust Co, arguing it could approve settlements that resolve disputed legal questions.
  • The PSC dismissed Enbridge’s complaint; on appeal the Court (Saad, J.) reviewed whether the PSC exceeded its statutory authority by approving an RDM for an electric utility via settlement and reversed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether PSC had authority to approve settlement implementing an RDM for an electric utility Enbridge: Act 295’s MCL 460.1097(4) does not authorize implementation; PSC exceeded statutory authority PSC: General rate-setting power and precedent (Dodge) allowed approval of settlement resolving legal dispute Court: PSC exceeded its statutory authority; Act 295 does not permit electric RDM implementation
Whether approval of an unlawful RDM via settlement is saved by settlement-doctrine Enbridge: Settlement cannot legalize an action contrary to clear statutory limits, especially where non-parties are bound PSC: Settlement resolves disputed legal issues and should be upheld under Dodge Court: Dodge inapposite — statute was clear, no reasonable dispute, and regulatory settlements bind many nonparties, so settlement cannot authorize ultra vires act
Whether PSC order dismissal for lack of standing was proper Enbridge: PSC should adjudicate complaint challenging PSC’s statutory authority PSC: Initially denied rehearing for lack of standing; later treated matter on motions and dismissed on merits Court: Reversed dismissal; substantive ruling that PSC lacked authority to approve RDM remains controlling
Standard of review applicable to PSC statutory authority Enbridge: De novo review of whether PSC exceeded statutory authority PSC: Deference to PSC statutory construction where ambiguous Court: De novo review for scope of authority; gave deference only where statute ambiguous — here statute clear against electric RDMs

Key Cases Cited

  • Detroit Edison Co. v. Public Service Commission, 296 Mich. App. 101 (court held MCL 460.1097(4) authorizes study/reporting only and not implementation of electric RDMs)
  • Dodge v. Detroit Trust Co., 300 Mich. 575 (settlement resolving disputed legal issue will generally be upheld)
  • Michigan Electric Cooperative Ass’n v. Public Service Commission, 267 Mich. App. 608 (agency has only authority expressly granted by Legislature)
  • In re MCI Telecommunications Complaint, 460 Mich. 396 (standard for overturning PSC orders; must follow mandatory statute or show abuse of discretion)
Read the full case

Case Details

Case Name: Enbridge Energy Limited Partnership v. Upper Peninsula Power Co
Court Name: Michigan Court of Appeals
Date Published: Dec 22, 2015
Citation: 313 Mich. App. 669
Docket Number: Docket 321946
Court Abbreviation: Mich. Ct. App.