History
  • No items yet
midpage
274 F. Supp. 3d 30
D.R.I.
2017
Read the full case

Background

  • Centredale Manor Superfund Site in North Providence, RI contains dioxin and other contaminants across a three-mile stretch including a defined Source Area, Allendale and Lyman Mill Ponds, and the Oxbow wetland.
  • EPA conducted an RI/FS, proposed a remedial plan (PRAP), amended it after a national dioxin reassessment, held notice-and-comment periods, and issued a Record of Decision (ROD) in Sept. 2012 selecting a multi-component remedy (excavation, confined disposal facility (CDF), RCRA C cap in Source Area, institutional controls, monitoring); estimated cost ~ $104.6M.
  • Emhart was found liable in Phase I for releases; in Phase II it challenged the lawfulness of EPA’s remedy selection and refused to comply with EPA’s June 10, 2014 Unilateral Administrative Order (UAO).
  • The court limited review generally to the administrative record but allowed expert testimony to aid understanding; it applied CERCLA’s record-review framework and the APA arbitrary-and-capricious standard (deferential but requires reasoned explanation).
  • The court found EPA followed CERCLA/NCP procedures overall but identified specific deficiencies in EPA’s analysis that rendered parts of the ROD arbitrary or inadequately justified on the existing record.

Issues

Issue Emhart's Argument Government's Argument Held
Scope of judicial review / supplementation of record Court should consider extra-record discovery and evidence to show flaws Judicial review under CERCLA is limited to the administrative record; supplementation allowed only narrowly Court: review limited to administrative record but may consider extra expert testimony to aid understanding; supplemental evidence otherwise disfavored absent bad faith or record inadequacy
Issue exhaustion (arguments raised first at trial) Court should consider Emhart’s newly raised objections to remedy Arguments not raised during PRAP comment period are waived; EPA should have opportunity to respond Court: generally enforces exhaustion; will consider only narrow exceptions for obvious/key assumptions that EPA must justify
Adequacy of site data / excavation & treatment volume estimates EPA lacked sufficient site-specific sampling to support FS/ROD estimates for excavation and off-site treatment quantities EPA had adequate sampling and may refine during remedial design; ROD permissibly reserved further sampling Court: EPA collected sufficient data to compare alternatives in FS and properly committed to additional remedial-design sampling; must update administrative record if design-stage data materially change costs or scope
Classification of Source Area groundwater as potential drinking water (Class II) Emhart: groundwater should be Class III (not a potential drinking source); Class II label drove stricter goals and RCRA C cap EPA: guidance supports Class II; classification consistent with NCP objectives and may be revised if design-stage data differ Court: EPA lacked sufficient analysis on vertical extent and off-site contributions to justify Class II; classification (and RCRA C cap tied to it) is arbitrary on present record and requires further analysis
Fish-consumption assumptions in BHHRA Emhart: EPA made unreasonable/speculative assumptions (species, portions consumed, and grams-from-site) inflating risk EPA: assumptions conservative, supported by literature/local expertise, and protect vulnerable subpopulations Court: most exposure assumptions defensible, but two arbitrary aspects: (1) excluding largemouth bass from Allendale despite evidence they likely exist; (2) relying on a 14 g/day per-person figure from MAS without accounting that MAS consumption is spread across waterbodies. EPA must correct these errors
Validity of UAO / Emhart’s refusal to comply Emhart: good-faith, objectively reasonable challenges to remedy justify non-compliance (i.e., "sufficient cause") EPA: UAO lawful; responsible parties must comply pending judicial review; penalties discretionary Court: Emhart’s noncompliance pursued in objective good faith given preserved challenges and some rulings in Emhart’s favor; UAO stayed pending EPA resolution of identified defects; accrued fines not imposed to date

Key Cases Cited

  • United States v. Bestfoods, 524 U.S. 51 (site cleanup authority and CERCLA purpose)
  • JG-24, Inc. v. United States, 478 F.3d 28 (administrative-review limited to the record under CERCLA)
  • Upper Blackstone Water Pollution Abatement Dist. v. EPA, 690 F.3d 9 (issue-exhaustion in notice-and-comment context)
  • Motor Vehicle Mfrs. Ass’n v. State Farm, 463 U.S. 29 (arbitrary and capricious/grounds for reversal)
  • Appalachian Power Co. v. EPA, 135 F.3d 791 (agency must justify key assumptions even if not objected to in comment)
  • Citizens to Preserve Overton Park v. Volpe, 401 U.S. 402 (record adequacy and supplementation exception)
  • Solid State Circuits, Inc. v. EPA, 812 F.2d 383 (sufficient-cause/good-faith basis to refuse UAO)
Read the full case

Case Details

Case Name: Emhart Industries, Inc. v. New England Container Co.
Court Name: District Court, D. Rhode Island
Date Published: Aug 17, 2017
Citations: 274 F. Supp. 3d 30; C.A. No. 06-218 S, C.A. No. 11-023 S
Docket Number: C.A. No. 06-218 S, C.A. No. 11-023 S
Court Abbreviation: D.R.I.
Log In